Temporary Closures on College, Meridian and Capitol


Red Line Acceleration

Beginning Monday, February 11, IndyGo Red Line contractors will be ramping up construction activity on the corridor to cut 4 months off the construction schedule.

The acceleration plan will shorten the duration of Red Line construction and reduce the time that residents experience inconveniences, allowing the Red Line to open by the end of the summer.

Full details here.


3 Week Look A-head


Want updates in your inbox?

Scroll to the bottom of the page to sign up!

The schedule below shows a three-week projection of construction activities.  As with all construction projects, the following forecast is subject to change.

Please be advised that reduced speed limits are posted, and will be enforced, within all construction zones.

May 20 Traffic Impacts:

Starting this week:

  • Pavement markings will be placed on Washington St. between Delaware St. and Capitol Ave. on (or after) May 20. This work is expected to be completed in two days.
  • There will be temporary lane restrictions and traffic shifts around work areas.

Starting this Week:

  • Virginia Avenue will be resurfaced beginning on or after May 22. Drivers should expect intermittent lane closures and flaggers around paving crews. Work will begin at Prospect Street and continue north to Maryland Street. On-street parking will be restricted during work activities. No parking signs will be posted 48-hours in advance of the work.
  • One lane of Virginia Avenue will be temporarily restricted near the Virginia Avenue stations this week for concrete work on the platforms. Flaggers will be used to direct traffic through the remaining open lane and around the work zones. This will take place:
    • At the Woodlawn Avenue stations on May 21
    • At the Merrill Street stations on May 23
    • At the New Jersey stations on May 29

Continuing Construction:

  • Construction of the station structures is continuing.

Coming Soon:

  • Pavement markings will be placed on Virginia Ave beginning on (or after) June 3. This work is expected to be completed in one week with short-term lane restrictions around work areas.

 

Continuing Construction:

  • Construction of the station structures is continuing.
  • Shelby Street is currently being resurfaced and pavement markings will be placed once paving is complete. There will be intermittent lane closures, traffic restrictions, and flaggers directing traffic around paving and striping crews. This work will continue through approximately June 1.

Starting this Week:

  • Starting on or after May 21, a half-block section of Walnut Street will be closed immediately east of Capitol Ave for up to 5 days. The Indianapolis Cultural Trail will remain open through this intersection.  Walnut Street will be open at Illinois Street and at Muskingum Street.

Continuing Construction:

  • Traffic lane and parking restrictions continue on Capitol Avenue from 19th to Washington Street through spring 2019. All driveways, entrances, and parking lots will be accessible on both the east and west sides of Capitol Ave.
  • Construction of the station structures is continuing.

Coming Soon:

  • Capitol Avenue will be resurfaced beginning on or after May 28 between Washington Street and 18th Street. There will be intermittent lane closures, traffic restrictions, and flaggers directing traffic around paving crews.

 

Starting this week:

  • Beginning on or after May 19, traffic patterns will shift at the 38th and Meridian Street intersection. Construction activities will shift to the east side of Meridian, south of 38th Street, and traffic will be moved west of that work zone.
  • Night work will begin on or after May 20 for bus pad construction. Work will start at the 18th Street intersection and proceed North to 38th Street. Each station area and adjacent intersection will be closed for one overnight and open from 7:00am to 8:00pm. All work will be completed within 1 week with no weekend closures.

Continuing Construction:

  • Pavement patching continues at locations along Meridian Street. Drivers should expect temporary lane restrictions at localized work areas.
  • Construction of the station structures is continuing.
  • Construction activities continue the east side of Meridian Street. One lane of traffic will be maintained in each direction during this phase of construction.
  • Left turns are restricted at the following locations:

• Northbound and southbound at 21st Street
• Northbound and southbound at 22nd Street
• Northbound and southbound at 28th Street
• Southbound at 29th Street
• Northbound at 30th Street
• Northbound and southbound at 32nd Street
• Northbound and southbound at 34th Street
• Northbound at 38th Street

Coming Soon:

Meridian Street will be resurfaced beginning on or after June 10. On-street parking will be restricted in work areas. Watch for posted No Parking signs.

Starting this Week:

  • Short-term lane restrictions will occur on College Avenue at station locations over the next several weeks. Dates of anticipated restrictions (subject to change) are as follows:
    • 42nd Street – one lane closure May 23 for up to 3 hours
    • 46th Street – one lane closure May 22 for up to 40 minutes
    • 52nd Street – one lane closure May 24 for up to 40 minutes

Continuing Construction:

  • Parking is restricted within construction areas but otherwise available to use. Please adhere to parking signage where posted.
  • Red Line stormwater, curb, signal, and sidewalk work is ongoing along College Avenue. Flashing arrow boards, construction barrels, flaggers, and/or traffic officers are being used to shift traffic around work areas. One lane of traffic will be maintained in each direction.
    • Where stormwater pipe crosses driveways, reconstruction of those driveway approaches will be necessary. Crews will make every effort possible to notify residents and businesses of impacts to their driveway prior to the work being conducted.
  • Construction will continue at the College Avenue stations. Traffic is shifted around work zones and turn lane restrictions are in place.

Coming Soon:

  • Short-term lane restrictions will occur on College Avenue at station locations over the next several weeks. Dates of anticipated restrictions (subject to change) are as follows:
    • 46th Street – one lane closure May 29 or up to 3 hours
    • 52nd Street – one lane closure May 31 for up to 3 hours
  • Beginning May 28 a one-block segment of College Avenue will be closed for one day adjacent to each station location to allow bus pads to be constructed. These closures will start at the 42nd Street station on or after May 28 and will continue north. One station area will be under construction per day. Closures will begin at approximately 7am and end by 8pm the same day.
  • College Avenue will be resurfaced between 38th Street and 66th Paving operations will begin on or after June 3. On-street parking will be restricted in work areas. Please be alert for No Parking signs to be posted 24 hours in advance.

Continuing Construction:

  • Construction of the Park Avenue Station on 38th Street continues with lane and turning restrictions.
  • Construction activities are taking place at the intersections of 38th Street with College Ave and Meridian Street as workers modify the medians. Drivers should expect lane shifts around work areas in this location.

Starting this Week:

  • 30th Street: Curb and sidewalk work will begin on 30th Street on or after May 20th, requiring some lane restrictions.

Continuing this Week:

  • Crews are modifying signals along Illinois St. No traffic restrictions are anticipated. Minor sidewalk and parking restrictions may be necessary.


Corridors Under Construction:

  • Meridian Street from 18th St. to 38th St.
  • Shelby St. from Hanna Ave. to Prospect St.
  • Capitol Ave. from 18th St. to Washington St.
  • Virginia Ave. from Shelby to Delaware St.
  • College Ave. from 38th St. to 66th St.
  • 38th Street from Illinois St to College Ave
  • Illinois Street, Washington St to 18th St
  • 30th Street, Meridian St. to Illinois St.

* See Construction Forecast below for details.


Interactive Construction Map

Use this map by scrolling and clicking on the construction icons to understand what is happening in a particular place.



Click the buttons below to toggle which map items to display on the map.


Anticipated Construction Schedule

Draft schedule does not include utility relocations which may occur at any time throughout the construction process. Additional detailed schedules within each segment will be provided no less than three weeks in advance of construction activities.



Construction Forecast 

January 7

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Fri 1/11
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Fri 1/11
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Fri 12/21
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 2/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Mon 12/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Mon 1/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 14

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 1/30
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Sat 1/26
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Tues 1/22
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/19
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Sat 2/2
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 21

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/6
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Wed 2/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Wed 1/30
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Mon 1/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/21
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Fri 2/8
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Wed 2/6
Station platform work @Southbound New Jersey: Wed 1/2 – Tues 2/12
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1
College Ave. from 50th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1

January 28

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Tues 2/12
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Fri 2/8
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Mon 2/4
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Sat 2/9
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Thurs 1/31
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Thurs 1/31
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Mon 2/4
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Tues 2/12
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Sat 2/9
Erect station structure @Northbound New Jersey: Mon 2/4 – Tues 2/19
Station platform work @Southbound New Jersey: Thurs 2/14 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @66th : Wed 2/6 – Thurs 2/28

February 4

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 –
Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 –
Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 –
Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 –
Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 –
Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 –
Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 –
Sat 3/9
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 –
Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 –
Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 –
Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 –
Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 –
Mon 2/11
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive):
Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station:
Thurs 2/7 – Sun 2/24
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 –
Sun 3/17
Station platform work @Northbound Virginia Ave. Station (Woodlawn):
Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Sat 4/20
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 –
Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey:
Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey:
Mon 2/4 – Mon 2/18
Station platform work @Southbound New Jersey: Thurs 2/14 –
Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 11

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/14
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Thu 3/14
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/15
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Wed 3/20
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 3/29
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Wed 2/6 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 18

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Sun 3/10
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Mon 2/25
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Sat 3/2
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Erect station structure @344th Street Station: Wed 2/13 – Thurs 3/21
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Sun 3/31
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Thurs 3/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/18 – Fri 4/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/27

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Northbound Virginia Ave. Station (Merrill): Fri 3/8 – Sun 4/7
Erect station structure @Southbound Virginia Ave. Station (Merrill): Wed 3/6 – Sun 3/31
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Tues 4/16
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Thurs 3/7
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 2/22
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 25

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Sun 3/10
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Thurs 2/28
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Sat 3/2
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Thurs 2/28
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Sun 3/31
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Thurs 3/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 3/15
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/18 – Wed 3/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Station platform work @Vermont Street Station: Wed 2/20 – Wed 3/20
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Mon 3/11 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/25 – Wed 3/6

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Northbound Virginia Ave. Station (Merrill): Fri 3/8 – Sun 4/7
Erect station structure @Southbound Virginia Ave. Station (Merrill): Wed 3/6 – Sun 3/31
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Tues 4/16
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Thurs 3/7
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 2/22
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Tues 3/5 – Mon 3/11
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Thurs 3/7 – Wed 3/13
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Wed 2/27 – Wed 3/6
Station platform work @Broad Ripple Ave. Station: Thurs 3/7 – Thurs 3/21
Station platform work @Kessler Ave. Station: Thurs 3/14 – Fri 4/5

 

 

 

March 4

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Wed 3/13
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Thurs 2/28
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 3/8
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Sat 3/9
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 3/11
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Wed 3/27
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/24
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Thurs 2/28 – Wed 3/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Station platform work @Vermont Street Station: Mon 3/11 – Tues 3/26
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Mon 4/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/25 – Mon 3/11

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 – Tues 4/23
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Fri 3/15
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 3/18
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Mon 3/18 – Tues 3/26
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Sat 3/16
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Sat 3/16
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Fri 3/15 – Sat 3/23
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform & ramp work @52nd Street Station: Wed 3/13 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Wed 3/6 – Mon 4/1
Station platform work @Broad Ripple Ave. Station: Fri 3/8 – Mon 3/25
Station platform work @Kessler Ave. Station: Fri 4/5 – Tues 4/30

March 11

Meridian Street from 18th St. to 38th St.
Station platform & ramp work @14th Street Station: Tues 2/19 –
Fri 4/5
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Wed 3/13
Station ramp work @34th Street Station: Mon 2/11 –
Fri 3/22
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 4/5
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 –
Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Wed 3/27

Shelby St. from Raymond St. to Prospect St.
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/24
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 –
Fri 3/22

Capitol Ave. from 18th St. to Washington St.
Station platform & ramp work @9th Street Station: Thurs 2/28 –
Sat 4/6
Erect station structure @9th Street Station: Thurs 3/21 – Mon 5/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 3/19 –
Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station structure @18th Street Station: Fri 3/15 – Wed 4/24
Station platform work @Vermont Street Station: Mon 3/11 – Sat 3/30
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Mon 4/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements:
Mon 3/11 – Wed 3/20

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –
Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
Wed 3/27
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Tues 3/19
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Thurs 3/21 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 –
Fri 3/22
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Fri 3/22
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey:
Thurs 3/21 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @Park Station: Mon 3/25 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/18 – Sat 3/23
Temporary road closure Bungalow Street east of College Ave: Mon 3/18 – Sat 3/23
Lane restriction from 38th Street to Ruckle Street: Mon 3/18 – Tues 4/30
Station platform & ramp work @52nd Street Station: Wed 3/20 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 –
Wed 3/13
Erect station structure @66th Street Station: Wed 3/20 – Fri 4/26
Station platform work @Broad Ripple Ave. Station: Tues 3/12 – Sat 3/30
Station platform work @Kessler Ave. Station: Fri 4/5 – Tues 4/30
Signal work: Mon 2/4 – Wed 5/1

March 18

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Station ramp work @34th Street Station: Mon 2/11 – Tues 3/19
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Thurs 3/28
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Fri 4/5
Bus pad work @Troy Avenue: Sat 3/17 – Tues 4/9
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 4/5
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Fri 3/29 – Mon 4/15
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Thurs 3/28 – Fri 5/10

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Station platform & ramp work @9th Street Station: Thurs 2/28 – Sat 4/6
Erect station structure @9th Street Station: Thurs 3/21 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 3/29
Erect station structure @14th Street Station: Tues 3/19 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station structure @18th Street Station: Fri 3/15 – Wed 4/24
Station platform work @Vermont Street Station: Mon 3/11 – Mon 4/8
Erect station structure @Vermont Street Station: Wed 4/3 – Fri 5/10
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/8
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 3/20

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Wed 3/20
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Wed 3/20
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 3/27
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Tues 3/19
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Wed 3/20 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/30 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Fri 3/22
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Fri 3/22
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/20 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @Park Station: Mon 3/25 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 3/20 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Fri 4/26
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 4/5
Station platform work @Broad Ripple Ave. Station: Mon 3/25 – Mon 4/8
Station platform work @Kessler Ave. Station: Wed 4/10 – Tues 4/30
Signal work: Mon 2/4 – Wed 5/1

March 25

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Tues 4/9 – Wed 4/17
Bus pad work @22nd Street Station: Mon 4/8 – Tues 4/16
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Sat 4/6 – Sun 4/14
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Wed 4/10 – Thurs 4/18
Bus pad work @34th Street Station: Thurs 4/11 – Fri 4/19
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Tues 4/9
Bus pad work @Troy Avenue: Fri 3/29 – Thurs 4/11
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Tues 4/9
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/15
Bus pad work @Shelby Street Station (Pleasant Run Drive): Wed 4/10 – Wed 4/17
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Sat 4/6
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Sat 4/6
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 4/5
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Thurs 4/18
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 – Mon 4/8
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Mon 3/25

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Mon 3/25
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 3/25
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Mon 3/25
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Mon 3/25
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform work @Park Station: Thurs 3/21 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Tues 4/16 – Tues 5/7
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: Mon 3/25 – Thurs 4/18
Station platform work @Kessler Ave. Station: Wed 5/1 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 1

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station:
Wed 4/10 – Thurs 4/11
Bus pad work @22nd Street Station:
Tues 4/9 – Wed 4/10
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station:
Mon 4/8 – Tues 4/9
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station:
Thurs 4/11 – Fri 4/12
Bus pad work @34th Street Station:
Fri 4/12 – Sat 4/13
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Tues 4/9
Bus pad work @Troy Avenue: Fri 3/29 – Thurs 4/11
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 –
Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/15
Bus pad work @Shelby Street Station (Pleasant Run Drive):
Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 –
Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – 
Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 –
Mon 4/8
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 4/5
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – 
Mon 4/22
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 –
Wed 4/10
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Mon 3/25

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
 Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – 
Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – 
Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – 
Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform work @Park Station: Thurs 3/21 –
Mon 4/15
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Tues 4/16 – Tues 5/7
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: Mon 3/25 – Thurs 4/18
Station platform work @Kessler Ave. Station: Wed 5/1 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 8

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: 
Tues 4/16 – Fri 4/19
Bus pad work @22nd Street Station: 
Mon 4/15 – Thurs 4/18
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: 
Mon 4/15 – Wed 4/17
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: 
Wed 4/17 – Sat 4/20
Bus pad work @34th Street Station: 
Thurs 4/18 – Tues 4/23
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue:
Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – 
Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Sat 4/20
Bus pad work @Raymond Street:
Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): 
Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – 
Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – 
Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – 
Fri 4/26
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 – 
Wed 4/10
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 –
Sat 4/13

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
 Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – 
Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 4/19 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform and ramp work @Park Station: Thurs 3/21 – 
Mon 4/15
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 5/1 – Tues 5/21
Station platform & ramp work @54th Street Station: Mon 4/22 – Wed 5/15

Station platform & ramp work @66th Street Station: Wed 2/13 – 
Mon 4/15
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: 
Thurs 4/4 – Fri 5/10
Station platform work @Kessler Ave. Station:
Wed 4/17 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 15

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Tues 4/23 – Tues 4/30
Bus pad work @22nd Street Station:  Mon 4/22 – Mon 4/29
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 4/22 – Mon 4/29
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Tues 4/2 – Wed 5/1
Bus pad work @34th Street Station: Thurs 4/25 – Thurs 5/2
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Mon 4/15
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Wed 5/1
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Fri 4/26
Erect station structure @Vermont Street Station: Mon 4/22 – Mon 5/13
Station platform & ramp work @Washington Street Station: Wed 3/6 – Tues 4/16
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sat 4/13

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 4/19 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform and ramp work @42nd Street Station: Wed 4/24 – Wed 5/1
Erect station platform @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Mon 4/29 – Tues 5/21
Station platform & ramp work @54th Street Station: Mon 4/22 – Wed 5/15
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/19
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Wed 5/1
Station platform work @Kessler Ave. Station: Tues 4/16 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

Washington, Delaware and Maryland Streets
Resurfacing work @Washington St.: Thurs 4/18 – Mon 5/6
Resurfacing work @Maryland St.: Thurs 4/18 – Mon 5/6
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

April 22

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Wed 5/15– Thurs 5/16
Bus pad work @22nd Street Station:  Tues 5/14 – Wed 5/15
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/13 – Tues 5/14
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Thurs 5/16 – Fri 5/17
Bus pad work @34th Street Station: Fri 5/17 – Fri 5/18
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 4/22 – Tues 4/23
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street : Fri 4/26 – Sat 4/27
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street : Fri 4/26 – Sat 4/27
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 5/6 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sun 5/5

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Wed 5/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Wed 5/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform and ramp work @42nd Street Station: Fri 5/3 – Wed 5/22
Erect station platform @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26  Tues 5/21
Station platform & ramp work @52nd Street Station: Mon 4/29 – Tues 5/21
Station platform & ramp work @54th Street Station: Wed 4/24 – Fri 5/17
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 4/25
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Fri 4/26
Station platform work @Kessler Ave. Station: Tues 4/16 – Fri 5/10
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

April 30

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: 
Thurs 5/23 – Fri 5/24
Bus pad work @22nd Street Station: 
Wed 5/22 – Thurs 5/23
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: 
Tues 5/21 – Wed 5/22
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: 
Fri 5/24 – Sat 5/25
Bus pad work @34th Street Station: 
Sat 5/25 – Sun 5/26
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street:
Mon 4/29 – Tues 4/30
Erect station structure @9th Street Station:
Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street :
Wed 5/1 – Thurs 5/2
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street :
Wed 5/1 – Thurs 5/2
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 –
Sun 5/15(Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 –
Sat 5/11

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Wed 5/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 –
Sat 5/18 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station structure @Kessler Station: Fri 5/3 – Tues 5/28
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/1
Erect station structure @52 nd Street Station: Wed 5/15 – Sat 6/15

Station platform and ramp work @42nd Street Station:
Thurs 5/9 – Tues 6/4
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 
Thurs 5/16
Station platform & ramp work @52nd Street Station: 
Wed 5/1 – Sat 5/25
Station platform & ramp work @54th Street Station:
Fri 5/10 – Sun 6/9
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 –
Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Fri 4/26
Station platform work @Kessler Ave. Station: Tues 4/16 – Fri 5/10
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

May 6

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Wed 5/29 – Thurs 5/30
Bus pad work @22nd Street Station:  Tues 5/28 – Wed 5/29
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/27 – Tues 5/28
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Mon 5/20 – Fri 5/31
Bus pad work @34th Street Station: Fri 5/31 – Sat 6/1
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/6 – Tues 5/7
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street: Mon 5/6 – Tues 5/7
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street: Wed 5/8 – Thurs 5/9
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Sun 5/15(Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sun 5/19

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Sun 5/19 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Sat 5/18 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station structure @Kessler Station: Fri 5/3 – Tues 5/28
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/1
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/15
Station platform and ramp work @42nd Street Station: Thurs 5/9 – Tues 6/4
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 – Mon 5/27
Station platform & ramp work @52nd Street Station: Wed 5/1 – Sat 5/25
Erect station structure @54th Street Station: Fri 5/10 – Sun 6/9
Station platform & ramp work @54th Street Station: Wed 4/24 – Wed 5/22
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Sun 5/5
Station platform work @Kessler Ave. Station: Tues 4/16 – Fri 5/24
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Tues 5/14 – Tues 5/14
Pavement work @Maryland St.: Mon 5/13 – Mon 5/13
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

May 13

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station:  Tues 5/21 – Wed 5/22
Bus pad work @22nd Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station:  Tues 5/21 – Wed 5/22
Bus pad work @34th Street Station:  Wed 5/22 – Thurs 5/23
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – June (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/13 – Wed 5/15
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street:  Mon 5/13 – Wed 5/15
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street: Tues 5/14 – Thurs 5/16
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Sun 6/2(Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sun 5/19

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Fri 5/24 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 5/24 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station structure @Kessler Station: Fri 5/3 – Tues 5/28
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/8
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/15
Erect station structure @42nd Street Station: Sat 5/11 – Mon 6/10
Station platform and ramp work @42nd Street Station: Thurs 5/9 – Tues 6/4
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 – Mon 5/27
Station platform & ramp work @52nd Street Station: Wed 5/1 – Thurs 5/30
Erect station structure @54th Street Station: Fri 5/10 – Sun 6/9
Station platform & ramp work @54th Street Station: Wed 4/24 – Wed 5/22
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Thurs 5/16
Station platform work @Kessler Ave. Station: Tues 4/16 – Thurs 5/16
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Tues 5/14 – Tues 5/14
Pavement work @Maryland St.: Mon 5/13 – Mon 5/13
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

30th Street from Meridian Street to Illinois Street

Roadway improvements: Mon 5/20 – Mon 5/27

May 20

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Wed 5/22 – Thurs 5/23
Bus pad work @22nd Street Station: Tues 5/21 – Wed 5/22
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Thurs 5/23 – Fri 5/24
Bus pad work @34th Street Station: Fri 5/24 – Sat 5/25
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – June (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 2/18 – Thurs 5/16

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Fri 5/17

Capitol Ave. from 18th St. to Washington St.
Closure @ Walnut Street: Tues 5/21 – Fri 5/24
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Fri 5/24
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/13 – Wed 5/15
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street:  Mon 5/13 – Wed 5/15
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street: Tues 5/14 – Thurs 5/16
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Wed 5/29
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Wed 6/19 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 6/5

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Thurs 5/23
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 – Thurs 5/23
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 5/21
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Tues 5/21
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Wed 6/12 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Wed 5/29
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Wed 5/29
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Wed 6/12 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Tues 6/25
Bus pad work @42nd Street Station: Tues 5/28 – Tues 5/28
Bus pad work @46th Street Station: Wed 5/29 – Wed 5/29
Bus pad work @52nd Street Station: Thurs 5/30 – Thurs 5/30
Bus pad work @54th Street Station: Fri 5/31 – Fri 5/31
Bus pad work @Kessler Ave. Station: Sat 6/1 – Sat 6/1
Bus pad work @Broad Ripple Ave. Station: Mon 6/3 – Mon 6/3
Erect station structure @Kessler Station: Wed 5/15 – Thurs 6/20
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/8
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/22
Erect station structure @42nd Street Station: Sat 5/11 – Sat 6/15
Station platform and ramp work @42nd Street Station: Wed 5/1 – Thurs 5/24
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 – Fri 5/24
Station platform & ramp work @52nd Street Station: Wed 5/1 – Sat 5/25
Erect station structure @54th Street Station: Fri 5/10 – Tues 6/11
Station platform & ramp work @54th Street Station: Wed 4/24 – Fri 5/17
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Thurs 5/16
Station platform work @Kessler Ave. Station: Tues 4/16 – Thurs 5/16
Signal work: Mon 2/4 – Sat 6/25

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Mon 5/20 – Thurs 5/23
Pavement work @Maryland St.: Wed 5/22 – Sat 6/1
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

30th Street from Meridian Street to Illinois Street

Roadway improvements: Mon 5/20 – Mon 5/27

 

 

Construction of the Red Line began in June 2018. You can view all published 2018 construction forecast here!

 