Temporary Closures on College, Meridian and Capitol


Red Line Acceleration

Beginning Monday, February 11, IndyGo Red Line contractors will be ramping up construction activity on the corridor to cut 4 months off the construction schedule.

The acceleration plan will shorten the duration of Red Line construction and reduce the time that residents experience inconveniences, allowing the Red Line to open by the end of the summer.

Full details here.


3 Week Look A-head


Want updates in your inbox?

Scroll to the bottom of the page to sign up!

The schedule below shows a three-week projection of construction activities.  As with all construction projects, the following forecast is subject to change.

Please be advised that reduced speed limits are posted, and will be enforced, within all construction zones.

April 22 Traffic Impacts:

Starting this week:

• Pavement resurfacing will be taking place on the following downtown roadway segments beginning on or after April 18:

  • Maryland St from Capitol Ave to Meridian St
  • Washington St from Capitol Ave to Delaware St

Drivers should expect temporary lane restrictions and traffic shifts around work areas.

Continuing Construction:

  •  Construction of the station structures is continuing.

Coming Soon:

  • Virginia Avenue will be resurfaced beginning on or after May 6. Drivers should expect intermittent lane closures and flaggers around paving crews.

Starting this Week:

  • A short-term closure (1-2 hours) of one lane of Shelby Street will be required at each station location when topping slabs are poured. This work will begin at Hanna Avenue. Crews will continue north from there. Drivers should be alert for flaggers directing traffic.
  • Shelby Street will be resurfaced beginning on or after April 26. Drivers should expect intermittent lane closures and flaggers around paving crews through approximately May 5.

Continuing Construction:

  • Construction of the station structures is continuing.

Starting this Week:

  • Please be alert for temporary lane restrictions at the station areas through April:
      • Construction has started on bus pads. During the week of April 22 segments of Capitol Ave immediately adjacent to the following stations will be reduced to a single lane to accommodate the work:
        • Vermont Street
        • 9th Street
        • 14th Street
        • 18th Street

Continuing Construction:

  • Pavement patching will continue at locations along Capitol Avenue through April. Drivers should expect temporary lane restrictions at localized work areas.
  • As construction crews continue progress on station foundations, drivers should continue to expect lane shifts. Station foundation work will continue through April. Parking spaces are restricted immediately adjacent to some station areas during this period.
  • Traffic lane and parking restrictions continue on Capitol Avenue from 19th to Washington Street through spring 2019. All driveways, entrances, and parking lots will be accessible on both the east and west sides of Capitol.

 

Continuing Construction:

  • Construction activities continue the east side of Meridian Street. One lane of traffic will be maintained in each direction during this phase of construction.
  • Left turns are restricted at the following locations:

• Northbound and southbound at 21st Street
• Northbound and southbound at 22nd Street
• Northbound and southbound at 28th Street
• Southbound at 29th Street
• Northbound at 30th Street
• Northbound and southbound at 32nd Street
• Northbound and southbound at 34th Street
• Northbound at 38th Street

Coming Soon:

  • Pavement patching will be occurring at locations along Meridian Street on or after May 6. Drivers should expect temporary lane restrictions at localized work areas.
  • Nighttime roadway closures will be required at station locations along Meridian Street between 18th and 38th Streets beginning on or after May 15 to facilitate construction of bus pads. These closures will occur between the hours of 9pm and 7am. Each station area and its immediately adjacent intersection will be closed for one night and reopened at 7am the next day. Night work along Meridian St will be completed in approximately 1 week.
  •  

Starting this Week:

  • Construction will start on the following stations beginning this week:
      • 54th Street – April 25
      • 46th Street – April 25
      • 42nd Street – April 25

Traffic will be shifted to the outside curb lanes to allow crews to work in the center of College Avenue at each station area. Turn lane restrictions will be in effect until construction of the station is complete. Each direction of College Ave will be restricted to one lane adjacent to the construction area. Drivers should expect increased congestion at these intersections.

Continuing Construction:

  • Parking is restricted within construction areas but otherwise available to use. Please adhere to parking signage where posted.
  • Red Line stormwater, curb, signal, and sidewalk work is ongoing along College Avenue. Flashing arrow boards, construction barrels, flaggers, and/or traffic officers are being used to shift traffic around work areas. One lane of traffic will be maintained in each direction.
  • Construction will continue at the 66th Street, Broad Ripple, and Kessler Avenue stations. Traffic is shifted around work zones and turn lane restrictions are in place.

Coming Soon:

  • Construction will start at the 52nd Street station beginning on or after April 29. Traffic will be shifted to the outside curb lanes to allow crews to work in the center of College Avenue. Turn lane restrictions will be in effect until construction of the station is complete.

Starting this Week:

  • A short-term closure (3-4 hours) of one lane of 38th Street will be necessary to set the station structure at Park Avenue. This work will take place outside of the morning and evening rush hours on or after April 22.

Continuing Construction:

  • Construction of the Park Avenue Station on 38th Street is underway with lane and turning restrictions. Work will continue through approximately mid-May.
  • Construction activities are taking place at the intersections of 38th Street with College Ave and Meridian Street as workers modify the medians. Drivers should expect lane shifts around work areas in this location.


Corridors Under Construction:

  • Meridian Street from 18th St. to 38th St.
  • Shelby St. from Hanna Ave. to Prospect St.
  • Capitol Ave. from 18th St. to Washington St.
  • Virginia Ave. from Shelby to Delaware St.
  • College Ave. from 38th St. to 66th St.
  • 38th Street from Illinois St to College Ave

* See Construction Forecast below for details.


Interactive Construction Map

Use this map by scrolling and clicking on the construction icons to understand what is happening in a particular place.



Click the buttons below to toggle which map items to display on the map.


Anticipated Construction Schedule

Draft schedule does not include utility relocations which may occur at any time throughout the construction process. Additional detailed schedules within each segment will be provided no less than three weeks in advance of construction activities.



Construction Forecast 

January 7

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Fri 1/11
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Fri 1/11
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Fri 12/21
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 2/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Mon 12/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Mon 1/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 14

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 1/30
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Sat 1/26
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Tues 1/22
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/19
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Sat 2/2
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 21

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/6
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Wed 2/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Wed 1/30
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Mon 1/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/21
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Fri 2/8
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Wed 2/6
Station platform work @Southbound New Jersey: Wed 1/2 – Tues 2/12
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1
College Ave. from 50th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1

January 28

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Tues 2/12
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Fri 2/8
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Mon 2/4
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Sat 2/9
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Thurs 1/31
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Thurs 1/31
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Mon 2/4
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Tues 2/12
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Sat 2/9
Erect station structure @Northbound New Jersey: Mon 2/4 – Tues 2/19
Station platform work @Southbound New Jersey: Thurs 2/14 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @66th : Wed 2/6 – Thurs 2/28

February 4

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 –
Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 –
Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 –
Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 –
Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 –
Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 –
Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 –
Sat 3/9
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 –
Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 –
Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 –
Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 –
Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 –
Mon 2/11
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive):
Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station:
Thurs 2/7 – Sun 2/24
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 –
Sun 3/17
Station platform work @Northbound Virginia Ave. Station (Woodlawn):
Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Sat 4/20
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 –
Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey:
Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey:
Mon 2/4 – Mon 2/18
Station platform work @Southbound New Jersey: Thurs 2/14 –
Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 11

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/14
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Thu 3/14
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/15
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Wed 3/20
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 3/29
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Wed 2/6 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 18

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Sun 3/10
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Mon 2/25
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Sat 3/2
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Erect station structure @344th Street Station: Wed 2/13 – Thurs 3/21
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Sun 3/31
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Thurs 3/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/18 – Fri 4/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/27

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Northbound Virginia Ave. Station (Merrill): Fri 3/8 – Sun 4/7
Erect station structure @Southbound Virginia Ave. Station (Merrill): Wed 3/6 – Sun 3/31
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Tues 4/16
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Thurs 3/7
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 2/22
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 25

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Sun 3/10
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Thurs 2/28
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Sat 3/2
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Thurs 2/28
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Sun 3/31
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Thurs 3/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 3/15
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/18 – Wed 3/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Station platform work @Vermont Street Station: Wed 2/20 – Wed 3/20
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Mon 3/11 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/25 – Wed 3/6

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Northbound Virginia Ave. Station (Merrill): Fri 3/8 – Sun 4/7
Erect station structure @Southbound Virginia Ave. Station (Merrill): Wed 3/6 – Sun 3/31
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Tues 4/16
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Thurs 3/7
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 2/22
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Tues 3/5 – Mon 3/11
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Thurs 3/7 – Wed 3/13
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Wed 2/27 – Wed 3/6
Station platform work @Broad Ripple Ave. Station: Thurs 3/7 – Thurs 3/21
Station platform work @Kessler Ave. Station: Thurs 3/14 – Fri 4/5

 

 

 

March 4

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Wed 3/13
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Thurs 2/28
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 3/8
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Sat 3/9
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 3/11
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Wed 3/27
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/24
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Thurs 2/28 – Wed 3/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Station platform work @Vermont Street Station: Mon 3/11 – Tues 3/26
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Mon 4/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/25 – Mon 3/11

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 – Tues 4/23
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Fri 3/15
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 3/18
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Mon 3/18 – Tues 3/26
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Sat 3/16
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Sat 3/16
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Fri 3/15 – Sat 3/23
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform & ramp work @52nd Street Station: Wed 3/13 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Wed 3/6 – Mon 4/1
Station platform work @Broad Ripple Ave. Station: Fri 3/8 – Mon 3/25
Station platform work @Kessler Ave. Station: Fri 4/5 – Tues 4/30

March 11

Meridian Street from 18th St. to 38th St.
Station platform & ramp work @14th Street Station: Tues 2/19 –
Fri 4/5
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Wed 3/13
Station ramp work @34th Street Station: Mon 2/11 –
Fri 3/22
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 4/5
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 –
Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Wed 3/27

Shelby St. from Raymond St. to Prospect St.
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/24
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 –
Fri 3/22

Capitol Ave. from 18th St. to Washington St.
Station platform & ramp work @9th Street Station: Thurs 2/28 –
Sat 4/6
Erect station structure @9th Street Station: Thurs 3/21 – Mon 5/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 3/19 –
Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station structure @18th Street Station: Fri 3/15 – Wed 4/24
Station platform work @Vermont Street Station: Mon 3/11 – Sat 3/30
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Mon 4/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements:
Mon 3/11 – Wed 3/20

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –
Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
Wed 3/27
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Tues 3/19
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Thurs 3/21 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 –
Fri 3/22
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Fri 3/22
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey:
Thurs 3/21 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @Park Station: Mon 3/25 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/18 – Sat 3/23
Temporary road closure Bungalow Street east of College Ave: Mon 3/18 – Sat 3/23
Lane restriction from 38th Street to Ruckle Street: Mon 3/18 – Tues 4/30
Station platform & ramp work @52nd Street Station: Wed 3/20 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 –
Wed 3/13
Erect station structure @66th Street Station: Wed 3/20 – Fri 4/26
Station platform work @Broad Ripple Ave. Station: Tues 3/12 – Sat 3/30
Station platform work @Kessler Ave. Station: Fri 4/5 – Tues 4/30
Signal work: Mon 2/4 – Wed 5/1

March 18

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Station ramp work @34th Street Station: Mon 2/11 – Tues 3/19
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Thurs 3/28
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Fri 4/5
Bus pad work @Troy Avenue: Sat 3/17 – Tues 4/9
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 4/5
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Fri 3/29 – Mon 4/15
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Thurs 3/28 – Fri 5/10

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Station platform & ramp work @9th Street Station: Thurs 2/28 – Sat 4/6
Erect station structure @9th Street Station: Thurs 3/21 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 3/29
Erect station structure @14th Street Station: Tues 3/19 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station structure @18th Street Station: Fri 3/15 – Wed 4/24
Station platform work @Vermont Street Station: Mon 3/11 – Mon 4/8
Erect station structure @Vermont Street Station: Wed 4/3 – Fri 5/10
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/8
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 3/20

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Wed 3/20
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Wed 3/20
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 3/27
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Tues 3/19
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Wed 3/20 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/30 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Fri 3/22
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Fri 3/22
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/20 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @Park Station: Mon 3/25 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 3/20 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Fri 4/26
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 4/5
Station platform work @Broad Ripple Ave. Station: Mon 3/25 – Mon 4/8
Station platform work @Kessler Ave. Station: Wed 4/10 – Tues 4/30
Signal work: Mon 2/4 – Wed 5/1

March 25

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Tues 4/9 – Wed 4/17
Bus pad work @22nd Street Station: Mon 4/8 – Tues 4/16
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Sat 4/6 – Sun 4/14
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Wed 4/10 – Thurs 4/18
Bus pad work @34th Street Station: Thurs 4/11 – Fri 4/19
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Tues 4/9
Bus pad work @Troy Avenue: Fri 3/29 – Thurs 4/11
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Tues 4/9
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/15
Bus pad work @Shelby Street Station (Pleasant Run Drive): Wed 4/10 – Wed 4/17
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Sat 4/6
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Sat 4/6
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 4/5
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Thurs 4/18
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 – Mon 4/8
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Mon 3/25

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Mon 3/25
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 3/25
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Mon 3/25
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Mon 3/25
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform work @Park Station: Thurs 3/21 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Tues 4/16 – Tues 5/7
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: Mon 3/25 – Thurs 4/18
Station platform work @Kessler Ave. Station: Wed 5/1 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 1

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station:
Wed 4/10 – Thurs 4/11
Bus pad work @22nd Street Station:
Tues 4/9 – Wed 4/10
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station:
Mon 4/8 – Tues 4/9
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station:
Thurs 4/11 – Fri 4/12
Bus pad work @34th Street Station:
Fri 4/12 – Sat 4/13
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Tues 4/9
Bus pad work @Troy Avenue: Fri 3/29 – Thurs 4/11
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 –
Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/15
Bus pad work @Shelby Street Station (Pleasant Run Drive):
Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 –
Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – 
Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 –
Mon 4/8
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 4/5
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – 
Mon 4/22
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 –
Wed 4/10
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Mon 3/25

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
 Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – 
Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – 
Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – 
Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform work @Park Station: Thurs 3/21 –
Mon 4/15
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Tues 4/16 – Tues 5/7
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: Mon 3/25 – Thurs 4/18
Station platform work @Kessler Ave. Station: Wed 5/1 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 8

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: 
Tues 4/16 – Fri 4/19
Bus pad work @22nd Street Station: 
Mon 4/15 – Thurs 4/18
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: 
Mon 4/15 – Wed 4/17
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: 
Wed 4/17 – Sat 4/20
Bus pad work @34th Street Station: 
Thurs 4/18 – Tues 4/23
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue:
Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – 
Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Sat 4/20
Bus pad work @Raymond Street:
Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): 
Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – 
Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – 
Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – 
Fri 4/26
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 – 
Wed 4/10
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 –
Sat 4/13

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
 Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – 
Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 4/19 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform and ramp work @Park Station: Thurs 3/21 – 
Mon 4/15
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 5/1 – Tues 5/21
Station platform & ramp work @54th Street Station: Mon 4/22 – Wed 5/15

Station platform & ramp work @66th Street Station: Wed 2/13 – 
Mon 4/15
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: 
Thurs 4/4 – Fri 5/10
Station platform work @Kessler Ave. Station:
Wed 4/17 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 15

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Tues 4/23 – Tues 4/30
Bus pad work @22nd Street Station:  Mon 4/22 – Mon 4/29
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 4/22 – Mon 4/29
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Tues 4/2 – Wed 5/1
Bus pad work @34th Street Station: Thurs 4/25 – Thurs 5/2
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Mon 4/15
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Wed 5/1
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Fri 4/26
Erect station structure @Vermont Street Station: Mon 4/22 – Mon 5/13
Station platform & ramp work @Washington Street Station: Wed 3/6 – Tues 4/16
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sat 4/13

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 4/19 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform and ramp work @42nd Street Station: Wed 4/24 – Wed 5/1
Erect station platform @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Mon 4/29 – Tues 5/21
Station platform & ramp work @54th Street Station: Mon 4/22 – Wed 5/15
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/19
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Wed 5/1
Station platform work @Kessler Ave. Station: Tues 4/16 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

Washington, Delaware and Maryland Streets
Resurfacing work @Washington St.: Thurs 4/18 – Mon 5/6
Resurfacing work @Maryland St.: Thurs 4/18 – Mon 5/6
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

Construction of the Red Line began in June 2018. You can view all published 2018 construction forecast here!

 

Interested in bid opportunities with IndyGo?

Please visit the main bid opportunities page on the IndyGo website for more information.