3 Week Look-Ahead

The schedule below shows a three-week projection of construction activities.  As with all construction projects, the following forecast is subject to change.

November 19:

Meridian Street from 18th St. to 38th St.

Station foundation work @Fall Creek Parkway Station: Mon, 11/19 – Fri, 12/21

Station foundation work @22nd Street Station: Mon, 11/26 – Fri, 12/21

Station foundation work @30th Street Station: Mon, 11/12 – Fri, 12/7

Station foundation work @34th Street Station: Mon, 11/5 – Fri, 11/30

Station foundation work @38th Street Station: Mon, 10/29 – Fri, 12/14

Roadway & Sidewalk improvements: Mon, 8/6 – December (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.

Station platform work @Hannah Avenue Station: Mon, 11/26 – Fri, 12/21

Station platform work @Southbound Troy Avenue Station: Mon, 10/22 – Fri, 12/7

Station foundation work @Northbound Troy Avenue Station: Mon, 11/5 – Fri, 11/23

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)

Station platform work @Northbound Shelby Station (Southern Ave. Station): Mon 11/19 – Fri, 12/14

Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri, 12/14

Station platform work @Southbound Shelby Street Station: Mon, 10/29 – Fri, 12/14

Station foundation work @Northbound Shelby Street Station: Mon, 10/29 – Fri, 12/16

Roadway & Sidewalk improvements: Mon, 10/22 – Fri 11/30

Shelby St. from Raymond St. to Prospect St.

Station foundation work @Northbound Shelby Street Station (Pleasant Run Drive):
Mon, 10/15 – Fri, 11/2

Station platform work @Northbound Shelby Street Station (Pleasant Run Drive):
Mon, 11/5 – Fri, 1/4

Capitol Ave. from 18th St. to Washington St.

Roadway & Sidewalk improvements: Mon 11/26 – Mon 12/31 (Additional Detail Below)

Virginia Ave. from Shelby to East St.

Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Below)

Virginia Ave. from East St. to Delaware St.

Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Below)

Traffic Impacts & Lane Restrictions

VIRGINIA AVENUE TRAFFIC IMPACTS:
Starting November 15th, Red Line construction crews will move to Virginia Avenue to begin preparations for station foundation work.

On or after Monday, November 26, drivers should expect lane shifts as full station work is underway. No lane restrictions or closures are anticipated on Virginia Avenue, and this phase is estimated to last through December.

CAPITOL AVENUE RESTRICTIONS:

On or after Monday, November 12, traffic lane restrictions will be necessary on the west side of Capitol Avenue from 18th to Washington Street through December 31, 2018.

Construction crews are relocating utilities, improving drainage, pavement, sidewalks, curbs, pedestrian crossings, and ADA ramps. Drivers should heed construction signs to divert to shifted travel lanes.

Parking will be restricted on both sides of Capitol during west side construction work, and the bike lane will be closed. All driveways, entrances, and parking lots will be accessible on both the east and west sides of Capitol.

MERIDIAN STREET RESTRICTIONS:

Starting on or after November 5, between 18th and 38th Street, drivers will notice traffic pattern shifts as crews begin work on Meridian Street station foundations. Vehicle travel will continue to be restricted to one lane in each direction. The travel lane restrictions also reduce parking and left turns in some portions of the construction area.

The construction is estimated to December 2018, weather permitting.
The work includes storm water improvements, road resurfacing, sidewalk and curb repairs as well as ADA ramps.

Crews are focusing on the west side of Meridian Street currently. After that work is completed, construction crews will work on the east side of the construction area.

These are the locations where left turns are restricted:

  • Northbound and southbound at 21st Street
  • Southbound and southbound at 22nd Street
  • Northbound and southbound at 28th Street
  • Southbound at 29th Street
  • Northbound at 30th Street
  • Northbound and southbound at 32nd Street
  • Northbound and southbound at 34th Street
  • Northbound at 38th Street

COLLEGE AVENUE UTILITY RELOCATIONS:

Water and gas utility relocation on College Avenue will begin in November, in advance of Red Line construction.

Crews will be relocating sections of water main and/or fire hydrants at the following intersections over the next several months, with gas main relocation to follow:

  • 42nd Street
  • 44th Street
  • 46th Street
  • 49th Street
  • 52nd Street
  • 54th Street
  • 56th Street
  • 57th Street
  • 61st Street
  • Broad Ripple Avenue
  • 66th Street

Work at each location is expected to take approximately 14 days.

Where necessary, flashing arrow boards, flaggers, and/or traffic officers will be used to divert vehicles around work zones. Travelers should expect possible on-street parking restrictions, traffic pattern shifts, or partial lane closures with flaggers.

One lane of traffic will be maintained in each direction of College Avenue through the morning and evening peak hours.

Water shut offs will be necessary to facilitate these relocations, but will occur overnight.  Property owners will be notified in advance by the utility if their service will be affected.

Want updates in your inbox?

Scroll to the bottom of the page to sign up!


Interactive Construction Map

Use this map by scrolling and clicking on the construction icons to understand what is happening in a particular place.



Click the buttons below to toggle which map items to display on the map.


Anticipated Construction Schedule

Draft schedule does not include utility relocations which may occur at any time throughout the construction process. Additional detailed schedules within each segment will be provided no less than three weeks in advance of construction activities.



Construction Forecast Archive 

May 31

Shelby Street from Hanna Avenue to Prospect Street
Drivers will notice advance construction signage and some traffic pattern adjustments starting as early as Thursday, 5/31.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements Monday, June 4, through Friday, June 15.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements Monday, June 11, through Friday, June 22.

Shelby St. from Raymond St. to Prospect St. 
Roadway and sidewalk improvements Monday, June 18, through Tuesday, July 3.

Drivers are asked to please move carefully as workers will likely be using flags to direct traffic.

June 11

Shelby Street from Hanna Avenue to Prospect Street
Drivers will notice advance construction signage and some traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 15.

Station work for the Southbound Troy Avenue Station may also start the week of June 11 as well. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements Monday, June 11, through Friday, June 22.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements Monday, June 18, through Tuesday, July 3.

June 18

Shelby Street from Hanna Avenue to Prospect Street
Advance Construction Signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, June 25, through Tuesday, July 10. Advance construction signs and traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 28. Station work for the Southbound Troy Avenue Station, week of June 25th. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 18, through Friday, July 6.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 18, through Tuesday, July 10.

June 25

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 28.

Station work for the Southbound Troy Avenue Station, week of June 25th. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

July 2

Shelby St. from Hanna Ave. to Prospect St.
Advance construction signs and traffic pattern adjustments are in place.

Meridian St. from 30th St. to 38th St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 6.

Station work for the Southbound Troy Avenue Station continues. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

July 9

Shelby St. from Hanna Ave. to Prospect St.
Advance construction signs and traffic pattern adjustments are in place.

Meridian St. from 30th Street to 38th St.
Roadway and sidewalk improvements, Monday, July 2, through Friday, July 20. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 20.

Station work for the Southbound Troy Avenue Station continues. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 27.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 27.

July 16

Shelby St. from Hanna Ave. to Prospect St.
Advance construction signs and traffic pattern adjustments are in place.

Meridian St. from 30th St. to 38th St.
Roadway and sidewalk improvements, Friday, August 3, through Friday, August 31. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 20.

Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

July 23

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Thursday, July 26, through Friday, August 31. Expect traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

Meridian St. from 18th St. to 30th St.
Roadway and sidewalk improvements, Thursday, July 26, through Friday, August 31. Expect traffic pattern adjustments.

July 30

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, July 30, through Friday, August 31. Expect traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

Meridian St. from 18th St. to 30th St.
Roadway and sidewalk improvements, Monday, July 30, through Friday, August 31. Expect traffic pattern adjustments.

August 6

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through Friday, August 31. Expect traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

Meridian St. from 18th St. to 30th St.
Roadway and sidewalk improvements, Monday, August 6, through Friday, August 31. Expect traffic pattern adjustments.

August 13

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December 1.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

August 20

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December 1.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

August 27

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 10, through Friday, October 19.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

MERIDIAN STREET:

Construction will reduce vehicle travel to one lane in each direction.
The travel lane restrictions also reduce parking and left turns in some portions of the construction area.

The construction is estimated to December 2018, weather permitting.
The work includes storm water improvements, road resurfacing, sidewalk and curb repairs as well as ADA ramps.

Crews are focusing on the west side of Meridian Street currently. After that work is completed, construction crews will work on the east side of the construction area.

There are eight (8) locations left turns are restricted:

  • Northbound at 21st Street
  • Southbound at 22nd Street
  • Northbound at 30th Street
  • Northbound and southbound at 32nd Street
  • Northbound and southbound at 34th Street
  • Northbound at 38th Street

38th Street at Meridian Street Lane Restriction

Starting Friday, August 24, Red Line construction will impact the southern eastbound lane on 38th Street at Meridian Street.

  • The lane restriction is expected to last no more than seven (7) days weather permitting.
  • Vehicles will still be able to make a right turn south on to Meridian Street.
  • Pedestrians should use sidewalk on northside of street.
  • Entrances to businesses will remain open.

September 3

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 10, through Friday, October 19.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Friday, September 7.

September 10

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 24, through Friday, November 2.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Wednesday, September 12.

September 17

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions.

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 24, through Friday, November 2.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Friday, October 19.

Shelby St. from Virginia Ave. to New Jersey St.
Sewer work, roadway and sidewalk improvements, maintenance of traffic signing, Monday, October 1, through Friday, November 16

September 24

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions.

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 24, through Friday, November 2.

Shelby St. from Nelson Ave. to Southern Ave.
Roadway and sidewalk improvements, Monday, October 1, through Friday, October 26.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Friday, October 19.

Shelby St. from Virginia Ave. to New Jersey St. 
Sewer work, roadway and sidewalk improvements, maintenance of traffic signing, Monday, October 8, through Friday, November 16

October 1

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions.

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, October 1, through Friday, November 9.

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Roadway and sidewalk improvements, Monday, October 15, through Friday, November 9.


Shelby St. from Raymond St. to Prospect St.

Roadway and sidewalk improvements, Monday, July 16, through Friday, October 19.

Shelby St. from Virginia Ave. to New Jersey St. 
Update: Work on Virginia Ave. will begin Nov. 5 at the earliest.

October 8

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.

Expect traffic pattern adjustments and turn restrictions. ( * Additional Detail Below)

Station foundation work for the Meridian Street at 38th Street Station, Monday, October 15, through Friday, November 2.

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, October 1, through Friday, November 9.

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave. )
Roadway and sidewalk improvements, Monday, October 15, through Friday, November 9.

Station foundation work for the Southbound Shelby at Raymond Avenue Station, Monday, October 8, through Friday, October 6.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Friday, October 26.

Station foundation work for the Northbound Shelby at Pleasant Run Drive Station, Monday, October 15, through Friday, November 2.

October 15

Meridian Street from 18th Street to 38th Street 
Station foundation work for the Meridian Street at 30th Street Station, Monday, October 29, through Friday, November 16.

Station foundation work for the Meridian Street at 34th Street Station, Monday, October 22, through Friday, November 9.

Station foundation work for the Meridian Street at 38th Street Station, Monday, October 15, through Friday, November 2.

Roadway and sidewalk improvements, Monday, August 6, through December. Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, October 1, through Friday, November 9.

Station foundation work for the Northbound Troy Avenue Station, Monday, October 22, through Friday, November 9.

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Roadway and sidewalk improvements, Monday, October 22, through Friday, November 9.

Station foundation work for the Southbound Shelby at Raymond Avenue Station, Monday, October 8, through Friday, October 26.

Station foundation work for the Northbound Shelby at Raymond Avenue Station, Monday, October 29, through Friday, November 16.

Shelby St. from Raymond St. to Prospect St.
Station foundation work for the Northbound Shelby at Pleasant Run Drive Station, Monday, October 15, through Friday, November 2.

Roadway and sidewalk improvements, Monday, July 16, through Friday, October 26.

October 22

Meridian Street from 18th Street to 38th Street

Station foundation work @30th Street Station: Monday, 11/12 – Friday, 12/5

Station foundation work @34th Street Station: Monday, 11/5 – Friday, 11/23

Station foundation work @38th Street Station: Monday, 10/29 – Friday, 11/16

Roadway & Sidewalk improvements: Monday, 8/6 – December (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.

Station platform work @Southbound Troy Avenue Station: Monday, 10/22 – Friday, 12/7

Station foundation work @Northbound Troy Avenue Station: Monday, 11/5 – Friday, 11/23

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)

Roadway & Sidewalk improvements: Monday, 10/22 – Friday 11/9

Station platform work @Southbound Shelby Street Station: Monday, 10/29 – Friday, 12/14

Station foundation work @Northbound Shelby Street Station: Monday, 10/29 – Friday, 12/16

Shelby St. from Raymond St. to Prospect St.

Station foundation work @Northbound Shelby Street Station (Pleasant Run Drive): Monday, 10/15 – Friday, 11/2

Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Monday, 11/5 – Friday, 1/4

October 29

October 29

Meridian Street from 18th Street to 38th Street

Station foundation work @30th Street Station: Monday, 11/12 – Friday, 12/5

Station foundation work @34th Street Station: Monday, 11/5 – Friday, 11/23

Station foundation work @38th Street Station: Monday, 10/29 – Friday, 11/16

Roadway & Sidewalk improvements: Monday, 8/6 – December (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.

Station platform work @Southbound Troy Avenue Station: Monday, 10/22 – Friday, 12/7

Station foundation work @Northbound Troy Avenue Station: Monday, 11/5 – Friday, 11/23

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)

Roadway & Sidewalk improvements: Monday, 10/22 – Friday 11/9

Station platform work @Southbound Shelby Street Station: Monday, 10/29 – Friday, 12/14

Station foundation work @Northbound Shelby Street Station: Monday, 10/29 – Friday, 12/16

Shelby St. from Raymond St. to Prospect St.

Station foundation work @Northbound Shelby Street Station (Pleasant Run Drive): Monday, 10/15 – Friday, 11/2

Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Monday, 11/5 – Friday, 1/4

November 5

Meridian Street from 18th Street to 38th Street

Station foundation work @30th Street Station: Mon, 11/12 – Fri, 12/5

Station foundation work @34th Street Station: Mon, 11/5 – Fri, 11/23

Station foundation work @38th Street Station: Mon, 10/29 – Wed, 11/21

Roadway & Sidewalk improvements: Mon, 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.

Station platform work @Southbound Troy Avenue Station: Mon, 10/22 – Fri, 12/7 

Station foundation work @Northbound Troy Avenue Station: Mon, 11/5 – Fri, 11/23

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)   

Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri, 12/14

Station platform work @Southbound Shelby Street Station: Mon, 10/29 – Fri, 12/14

Station foundation work @Northbound Shelby Street Station: Mon, 10/29 – Fri, 12/16

Roadway & Sidewalk improvements: Mon, 10/22 – Fri 11/9

Shelby St. from Raymond St. to Prospect St.

Station foundation work @Northbound Shelby Street Station (Pleasant Run Drive): Mon, 10/15 – Fri, 11/2

Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon, 11/5 – Fri, 1/4

November 12

Meridian Street from 18th St. to 38th St.

Station foundation work @Fall Creek Parkway Station: Mon, 11/19 – Fri, 12/21

Station foundation work @22nd Street Station: Mon, 11/26 – Fri, 12/21

Station foundation work @30th Street Station: Mon, 11/12 – Fri, 12/5

Station foundation work @34th Street Station: Mon, 11/5 – Fri, 11/23

Station foundation work @38th Street Station: Mon, 10/29 – Fri, 11/30

Roadway & Sidewalk improvements: Mon, 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.   

Station platform work @Hannah Avenue Station: Mon, 11/26 – Fri, 12/21

Station platform work @Southbound Troy Avenue Station: Mon, 10/22 – Fri, 12/7 

Station foundation work @Northbound Troy Avenue Station: Mon, 11/5 – Fri, 11/23

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)   

Station platform work @Northbound Shelby Station (Southern Ave. Station): Mon 11/19 – Fri, 12/14

Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri, 12/14

Station platform work @Southbound Shelby Street Station: Mon, 10/29 – Fri, 12/14

Station foundation work @Northbound Shelby Street Station: Mon, 10/29 – Fri, 12/16

Roadway & Sidewalk improvements: Mon, 10/22 – Fri 11/16

Shelby St. from Raymond St. to Prospect St.

Station foundation work @Northbound Shelby Street Station (Pleasant Run Drive): Mon, 10/15 – Fri, 11/2

Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon, 11/5 – Fri, 1/4

Capital Ave. from 18th St. to Washington St.

Roadway & Sidewalk improvements: Mon 11/19 – Mon 12/31

November 19

Meridian Street from 18th St. to 38th St.

Station foundation work @Fall Creek Parkway Station: Mon, 11/19 – Fri, 12/21

Station foundation work @22nd Street Station: Mon, 11/26 – Fri, 12/21

Station foundation work @30th Street Station: Mon, 11/12 – Fri, 12/7

Station foundation work @34th Street Station: Mon, 11/5 – Fri, 11/30

Station foundation work @38th Street Station: Mon, 10/29 – Fri, 12/14

Roadway & Sidewalk improvements: Mon, 8/6 – December (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.

Station platform work @Hannah Avenue Station: Mon, 11/26 – Fri, 12/21
Station platform work @Southbound Troy Avenue Station: Mon, 10/22 – Fri, 12/7

Station foundation work @Northbound Troy Avenue Station: Mon, 11/5 – Fri, 11/23

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)

Station platform work @Northbound Shelby Station (Southern Ave. Station): Mon 11/19 – Fri, 12/14

Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri, 12/14

Station platform work @Southbound Shelby Street Station: Mon, 10/29 – Fri, 12/14

Station foundation work @Northbound Shelby Street Station: Mon, 10/29 – Fri, 12/16

Roadway & Sidewalk improvements: Mon, 10/22 – Fri 11/30

Shelby St. from Raymond St. to Prospect St.

Station foundation work @Northbound Shelby Street Station (Pleasant Run Drive):
Mon, 10/15 – Fri, 11/2

Station platform work @Northbound Shelby Street Station (Pleasant Run Drive):
Mon, 11/5 – Fri, 1/4

Capitol Ave. from 18th St. to Washington St.

Roadway & Sidewalk improvements: Mon 11/26 – Mon 12/31

Virginia Ave. from Shelby to East St.

Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.

Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1