Temporary Stop Closure on Meridian Street at 38th Street Begins Monday, September 17.

 


3 Week Look-Ahead

The schedule below shows a three-week projection of construction activities.  As with all construction projects, the following forecast is subject to change.

September 17

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 24, through Friday, November 2.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Friday, October 19.

Shelby St. from Virginia Ave. to New Jersey St.
Sewer work, roadway and sidewalk improvements, maintenance of traffic signing, Monday, October 1, through Friday, November 16

SERVICE MODIFICATION:

Effective Monday, September 17, 2018, the inbound stop on Meridian Street at 38th Street will be closed.

All inbound buses for routes 19 and 39 will run on a slight detour to serve the shelter on WESTBOUND 38th Street & Meridian Street (northwest corner).

Inbound stop will remain open on Meridian at 36th Street. Learn more.

MERIDIAN STREET:

Red Line bus rapid transit (BRT) construction on Meridian Street from 18th Street to 38th Street is underway and will reduce vehicle travel to one lane in each direction. The travel lane restrictions also reduce parking and left turns in some portions of the construction area.

The construction is estimated to December 2018, weather permitting.
The work includes storm water improvements, road resurfacing, sidewalk and curb repairs as well as ADA ramps.

Crews are focusing on the west side of Meridian Street currently. After that work is completed, construction crews will work on the east side of the construction area.

There are eight (8) locations left turns are restricted:

  • Northbound at 21st Street
  • Southbound at 22nd Street
  • Northbound at 30th Street
  • Northbound and southbound at 32nd Street
  • Northbound and southbound at 34th Street
  • Northbound at 38th Street

38th Street at Meridian Street Lane Restriction

As Red Line construction on 38th Street at Meridian is underway, lane restrictions will impact the southern eastbound lane on 38th Street at Meridian Street.

  • The lane restriction is expected to last until Friday, September 24, weather permitting.
  • Vehicles will still be able to make a right turn south on to Meridian Street.
  • Pedestrians should use sidewalk on northside of street.
  • Entrances to businesses will remain open.
Want updates in your inbox?

Scroll to the bottom of the page to sign up!


Interactive Construction Map

Use this map by scrolling and clicking on the construction icons to understand what is happening in a particular place.



Click the buttons below to toggle which map items to display on the map.


Anticipated Construction Schedule

Draft schedule does not include utility relocations which may occur at any time throughout the construction process. Additional detailed schedules within each segment will be provided no less than three weeks in advance of construction activities.



Construction Forecast Archive 

May 31

Shelby Street from Hanna Avenue to Prospect Street
Drivers will notice advance construction signage and some traffic pattern adjustments starting as early as Thursday, 5/31.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements Monday, June 4, through Friday, June 15.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements Monday, June 11, through Friday, June 22.

Shelby St. from Raymond St. to Prospect St. 
Roadway and sidewalk improvements Monday, June 18, through Tuesday, July 3.

Drivers are asked to please move carefully as workers will likely be using flags to direct traffic.

June 11

Shelby Street from Hanna Avenue to Prospect Street
Drivers will notice advance construction signage and some traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 15.

Station work for the Southbound Troy Avenue Station may also start the week of June 11 as well. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements Monday, June 11, through Friday, June 22.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements Monday, June 18, through Tuesday, July 3.

June 18

Shelby Street from Hanna Avenue to Prospect Street
Advance Construction Signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, June 25, through Tuesday, July 10. Advance construction signs and traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 28. Station work for the Southbound Troy Avenue Station, week of June 25th. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 18, through Friday, July 6.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 18, through Tuesday, July 10.

June 25

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 28.

Station work for the Southbound Troy Avenue Station, week of June 25th. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

July 2

Shelby St. from Hanna Ave. to Prospect St.
Advance construction signs and traffic pattern adjustments are in place.

Meridian St. from 30th St. to 38th St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 6.

Station work for the Southbound Troy Avenue Station continues. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 13.

July 9

Shelby St. from Hanna Ave. to Prospect St.
Advance construction signs and traffic pattern adjustments are in place.

Meridian St. from 30th Street to 38th St.
Roadway and sidewalk improvements, Monday, July 2, through Friday, July 20. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 20.

Station work for the Southbound Troy Avenue Station continues. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 27.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, July 27.

July 16

Shelby St. from Hanna Ave. to Prospect St.
Advance construction signs and traffic pattern adjustments are in place.

Meridian St. from 30th St. to 38th St.
Roadway and sidewalk improvements, Friday, August 3, through Friday, August 31. Expect advance construction signs and traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 20.

Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

July 23

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Thursday, July 26, through Friday, August 31. Expect traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

Meridian St. from 18th St. to 30th St.
Roadway and sidewalk improvements, Thursday, July 26, through Friday, August 31. Expect traffic pattern adjustments.

July 30

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, July 30, through Friday, August 31. Expect traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

Meridian St. from 18th St. to 30th St.
Roadway and sidewalk improvements, Monday, July 30, through Friday, August 31. Expect traffic pattern adjustments.

August 6

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through Friday, August 31. Expect traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

Meridian St. from 18th St. to 30th St.
Roadway and sidewalk improvements, Monday, August 6, through Friday, August 31. Expect traffic pattern adjustments.

August 13

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December 1.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

August 20

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December 1.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby Street from Hanna Avenue to Prospect Street
Advance construction signs and traffic pattern adjustments are in place.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, July 23, through Friday, August 10.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 10.

August 27

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 10, through Friday, October 19.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, August 31.

MERIDIAN STREET:

Construction will reduce vehicle travel to one lane in each direction.
The travel lane restrictions also reduce parking and left turns in some portions of the construction area.

The construction is estimated to December 2018, weather permitting.
The work includes storm water improvements, road resurfacing, sidewalk and curb repairs as well as ADA ramps.

Crews are focusing on the west side of Meridian Street currently. After that work is completed, construction crews will work on the east side of the construction area.

There are eight (8) locations left turns are restricted:

  • Northbound at 21st Street
  • Southbound at 22nd Street
  • Northbound at 30th Street
  • Northbound and southbound at 32nd Street
  • Northbound and southbound at 34th Street
  • Northbound at 38th Street

38th Street at Meridian Street Lane Restriction

Starting Friday, August 24, Red Line construction will impact the southern eastbound lane on 38th Street at Meridian Street.

  • The lane restriction is expected to last no more than seven (7) days weather permitting.
  • Vehicles will still be able to make a right turn south on to Meridian Street.
  • Pedestrians should use sidewalk on northside of street.
  • Entrances to businesses will remain open.

September 3

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements extended through Friday, July 27.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 10, through Friday, October 19.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Friday, September 7.

September 10

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions. (Additional Detail Below)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 24, through Friday, November 2.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Wednesday, September 12.

September 17

Meridian Street from 18th Street to 38th Street
Roadway and sidewalk improvements, Monday, August 6, through December.
Expect traffic pattern adjustments and turn restrictions.

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work for the Southbound Troy Avenue Station, Monday, September 24, through Friday, November 2.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 25, through Friday, September 21.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, July 16, through Friday, October 19.

Shelby St. from Virginia Ave. to New Jersey St.
Sewer work, roadway and sidewalk improvements, maintenance of traffic signing, Monday, October 1, through Friday, November 16