IndyGo’s Red Line Project Begins Construction!

 


3 Week Look-Ahead

The schedule below shows a three-week projection of construction activities.  As with all construction projects, the following forecast is subject to change.

June 18, 2018

Shelby Street from Hanna Avenue to Prospect Street
Advance Construction Signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, June 25, through Tuesday, July 10. Advance construction signs and traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 28.

Station work for the Southbound Troy Avenue Station, week of June 25th. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 18, through Friday, July 6.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 18, through Tuesday, July 10.

Want updates in your inbox?

Scroll to the bottom of the page to sign up!


Interactive Construction Map

Use this map by scrolling and clicking on the construction icons to understand what is happening in a particular place.



Click the buttons below to toggle which map items to display on the map.


Anticipated Construction Schedule

Draft schedule does not include utility relocations which may occur at any time throughout the construction process. Additional detailed schedules within each segment will be provided no less than three weeks in advance of construction activities.



Construction Forecast Archive 

May 31

Shelby Street from Hanna Avenue to Prospect Street
Drivers will notice advance construction signage and some traffic pattern adjustments starting as early as Thursday, 5/31.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements Monday, June 4, through Friday, June 15.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements Monday, June 11, through Friday, June 22.

Shelby St. from Raymond St. to Prospect St. 
Roadway and sidewalk improvements Monday, June 18, through Tuesday, July 3.

Drivers are asked to please move carefully as workers will likely be using flags to direct traffic.

June 11

Shelby Street from Hanna Avenue to Prospect Street
Drivers will notice advance construction signage and some traffic pattern adjustments.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 15.

Station work for the Southbound Troy Avenue Station may also start the week of June 11 as well. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements Monday, June 11, through Friday, June 22.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements Monday, June 18, through Tuesday, July 3.

June 18

Shelby Street from Hanna Avenue to Prospect Street
Advance Construction Signs and traffic pattern adjustments are in place.

Meridian Street from 30th Street to 38th Street
Roadway and sidewalk improvements, Monday, June 25, through Tuesday, July 10. Advance construction signs and traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Hanna Ave. to Troy Ave.
Roadway and sidewalk improvements, Monday, June 4, through Friday, June 28. Station work for the Southbound Troy Avenue Station, week of June 25th. Traffic shifts may be anticipated to facilitate that new work.

Shelby St. from Troy Ave. to Raymond St.
Roadway and sidewalk improvements, Monday, June 18, through Friday, July 6.

Shelby St. from Raymond St. to Prospect St.
Roadway and sidewalk improvements, Monday, June 18, through Tuesday, July 10.

Interested in bid opportunities with IndyGo?

Please visit the main bid opportunities page on the IndyGo website for more information.