IndyGo announces Red Line construction acceleration plan


Red Line Acceleration

Beginning Monday, February 11, IndyGo Red Line contractors will be ramping up construction activity on the corridor to cut 4 months off the construction schedule.

The acceleration plan will shorten the duration of Red Line construction and reduce the time that residents experience inconveniences, allowing the Red Line to open by the end of the summer.

Full details here.


3 Week Look A-head


Want updates in your inbox?

Scroll to the bottom of the page to sign up!

 

The schedule below shows a three-week projection of construction activities.  As with all construction projects, the following forecast is subject to change.

February 18 Traffic Impacts:

VIRGINIA AVENUE & SHELBY STREET TRAFFIC IMPACTS: As construction crews continue progress on utility relocations and station foundations, drivers should continue to expect lane shifts.

Virginia Avenue Update:

Virginia Avenue is currently closed for approximately one block north of Merrill Street to facilitate station construction. Access to all businesses, residences, and other properties will always be maintained. The Cultural Trail will remain open through construction.  This segment of roadway will open again before the end of March.

As construction crews continue progress on station foundations, drivers should continue to expect lane shifts. Station foundation work will continue at the Woodlawn and New Jersey Street stations. Parking spaces will be restricted immediately adjacent to the station areas during this period.

Shelby Street Update:

Drivers will notice lane shifts on Shelby St. at East Pleasant Run Parkway North Dr. as construction crews work on stations. No change to turning movements or travel patterns. Crews will begin asphalt patching on or after Feb 18 between Hanna Ave and Virginia Ave.

Traffic lane and parking restrictions continue on Capitol Avenue from 19th to Washington Street through Spring 2019. Two southbound travel lanes will remain open. Parking will be restricted on one side of Capitol during construction work, and the bike lane will be closed. All driveways, entrances, and parking lots will be accessible on both the east and west sides of Capitol.

Travelers should expect on-street parking restrictions adjacent to work zones. For the safety of our workers and drivers, please comply with no parking signage.

Between 18th and 38th Street, drivers should continue to expect traffic pattern shifts as crews continue work on Meridian Street stations. Vehicle travel will continue to be restricted to one lane in each direction. The travel lane restrictions also reduce parking and left turns in some portions of the construction area.

These are the locations where left turns are restricted:
• Northbound and southbound at 21st Street
• Southbound and southbound at 22nd Street
• Northbound and southbound at 28th Street
• Southbound at 29th Street
• Northbound at 30th Street
• Northbound and southbound at 32nd Street
• Northbound and southbound at 34th Street
• Northbound at 38th Street

Meridian Street Update:

Construction activities will be shifting to the east side of Meridian Street on or after March 4th.  Drivers should expect lane shifts. One lane of traffic will be maintained along the west side of Meridian Street during this phase of construction. Asphalt patching will also begin on or after March 4th between 18th and 38th Streets.

Crews continue water and gas utility relocations on College Avenue. Work at each location is expected to take approximately 14 days. Shut offs will be necessary to facilitate these relocations. Property owners will be notified in advance by the utility if their service will be affected.

Red Line stormwater, curb, signal, and sidewalk work has begun on College Avenue. Flashing arrow boards, construction barrels, flaggers, and/or traffic officers are being used to shift traffic around work areas. One lane of traffic will be maintained in each direction.

Foundation work has started at the 66th Street station. Travelers should expect traffic pattern shifts at this location.

College Ave Update:

51st Street will be closed immediately adjacent to College Ave (both east and west) on Monday Feb 18th for up to four hours (each side). This closure is necessary to upgrade drainage infrastructure.

A section of 52nd Street will be closed just west of College Ave for up to four days beginning on or after Wednesday Feb 20th. All businesses on 52nd Street will be accessible during the closure. The closure is necessary to upgrade drainage infrastructure, curbs, and sidewalk.

Travelers should expect on-street parking restrictions in all work zones (marked by orange barrels / barricades), although parking restrictions will be lifted outside of active work areas this week.  Please comply with all signage regarding on-street parking. Parking will be permitted along College outside of construction areas, unless otherwise signed.

Parking meters along College Ave, in the vicinity of Broad Ripple Avenue will be restricted for approximately 3 weeks beginning on or after March 25th.

Travelers should expect changing traffic patterns and lane shifts as construction progresses. Please use caution, reduce speeds, and stay alert for changes. To minimize disruptions, constructions zones will move as work is completed. While this reduces impact to residential parking, it does require driver attention. We appreciate your patience and compliance with signage.

Work south of 50th Street to 38th Street will begin in early March.


Corridors Under Construction:

  • Meridian Street from 18th St. to 38th St.
  • Shelby St. from Hanna Ave. to Prospect St.
  • Capitol Ave. from 18th St. to Washington St.
  • Virginia Ave. from Shelby to Delaware St.
  • College Ave. from 38th St. to 66th St.
  • 18th Street from Capitol Ave to Meridian St. (Currently closed to traffic. Expected to re-open in April)

* See Construction Archive below for details.


Interactive Construction Map

Use this map by scrolling and clicking on the construction icons to understand what is happening in a particular place.



Click the buttons below to toggle which map items to display on the map.


Anticipated Construction Schedule

Draft schedule does not include utility relocations which may occur at any time throughout the construction process. Additional detailed schedules within each segment will be provided no less than three weeks in advance of construction activities.



Construction Forecast Archive 

January 7

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Fri 1/11
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Fri 1/11
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Fri 12/21
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 2/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Mon 12/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Mon 1/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 14

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 1/30
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Sat 1/26
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Tues 1/22
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/19
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Sat 2/2
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 21

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/6
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Wed 2/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Wed 1/30
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Mon 1/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/21
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Fri 2/8
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Wed 2/6
Station platform work @Southbound New Jersey: Wed 1/2 – Tues 2/12
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1
College Ave. from 50th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1

January 28

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Tues 2/12
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Fri 2/8
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Mon 2/4
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Sat 2/9
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Thurs 1/31
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Thurs 1/31
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Mon 2/4
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Tues 2/12
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Sat 2/9
Erect station structure @Northbound New Jersey: Mon 2/4 – Tues 2/19
Station platform work @Southbound New Jersey: Thurs 2/14 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @66th : Wed 2/6 – Thurs 2/28

February 4

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 –
Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 –
Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 –
Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 –
Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 –
Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 –
Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 –
Sat 3/9
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 –
Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 –
Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 –
Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 –
Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 –
Mon 2/11
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive):
Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station:
Thurs 2/7 – Sun 2/24
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 –
Sun 3/17
Station platform work @Northbound Virginia Ave. Station (Woodlawn):
Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Sat 4/20
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 –
Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey:
Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey:
Mon 2/4 – Mon 2/18
Station platform work @Southbound New Jersey: Thurs 2/14 –
Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 11

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/14
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Thu 3/14
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/15
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Wed 3/20
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 3/29
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Wed 2/6 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 18

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Sun 3/10
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Mon 2/25
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Sat 3/2
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Erect station structure @344th Street Station: Wed 2/13 – Thurs 3/21
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Sun 3/31
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Thurs 3/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/18 – Fri 4/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/27

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Northbound Virginia Ave. Station (Merrill): Fri 3/8 – Sun 4/7
Erect station structure @Southbound Virginia Ave. Station (Merrill): Wed 3/6 – Sun 3/31
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Tues 4/16
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Thurs 3/7
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 2/22
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

Construction of the Red Line began in June 2018. You can view all published 2018 construction forecast here!

 