Corridor Wide Progress - Red Line Construction Reminders


Red Line Acceleration

Beginning Monday, February 11, IndyGo Red Line contractors will be ramping up construction activity on the corridor to cut 4 months off the construction schedule.

The acceleration plan will shorten the duration of Red Line construction and reduce the time that residents experience inconveniences, allowing the Red Line to open by the end of the summer.

Full details here.


3 Week Look A-head


Want updates in your inbox?

Scroll to the bottom of the page to sign up!

The schedule below shows a three-week projection of construction activities.  As with all construction projects, the following forecast is subject to change.

Please be advised that reduced speed limits are posted, and will be enforced, within all construction zones.

June 17 Traffic Impacts:

Continuing Construction:

  • Pavement markings are being placed on Washington St. between Delaware St. and Capitol Ave.
  • There will be temporary lane restrictions and traffic shifts around work areas.

Coming Soon:

  • Additional pavement markings will be placed in the bus lanes early in July.

Continuing Construction:

  • Pavement markings are being placed on Virginia Avenue. This work is expected to be completed this week, with short-term lane restrictions and temporary traffic controls around work areas.
  • Construction of the station structures is continuing.

Continuing Construction:

  • Construction of the station structures is continuing.
  • Shelby Street pavement markings are being installed this week. There will be short-term lane restrictions and temporary traffic controls around work areas.

Continuing Construction:

  • A half-block section of Walnut Street is closed immediately east of Capitol Ave through approximately the end of this week. The Indianapolis Cultural Trail remains open through this intersection.  Walnut Street is open at Illinois Street and at Muskingum Street.
  • Traffic lane and parking restrictions continue on Capitol Avenue from 19th to Washington Streets. All driveways, entrances, and parking lots will be accessible on both the east and west sides of Capitol Ave.
  • Construction of the station structures is continuing.

Coming Soon:

  • Traffic lane and parking restrictions continue on Capitol Avenue from 19th to Washington Streets. All driveways, entrances, and parking lots will be accessible on both the east and west sides of Capitol Ave.
  • Construction of the station structures is continuing.

Continuing Construction:

  • Construction of the station structures is continuing.
  • Construction activities continue on the east side of Meridian Street. One lane of traffic will be maintained in each direction during this phase of construction.
  • Left turns are restricted at the following locations:

• Northbound and southbound at 21st Street
• Northbound and southbound at 22nd Street
• Northbound and southbound at 28th Street
• Southbound at 29th Street
• Northbound at 30th Street
• Northbound and southbound at 32nd Street
• Northbound and southbound at 34th Street
• Northbound at 38th Street

Coming Soon:

  • Meridian Street will be re-paved starting in late June or July. Temporary lane restrictions and temporary traffic controls will be required around work areas.

Starting this Week:

  • One-block segments of College Avenue will be temporarily restricted adjacent to each station location over the next several weeks for up to two hours each. This will allow the final layer of concrete to be poured on the station platforms. A tentative schedule for this week is below:
    • 66th Street station on June 14
    • Broad Ripple Avenue station on June 21
  • Pavement resurfacing will begin has started on College Avenue at 66th Street. Work will continue south to 38th Street, taking approximately four weeks to complete. Temporary on-street parking and traffic restrictions will be required at work areas. Drivers should expect to encounter temporary traffic controls and/or lane closures. At times, drivers may be diverted off College Avenue.

Continuing Construction:

  • Pavement patching will continue on College Avenue this week. Drivers should expect temporary lane restrictions and parking restrictions at localized work areas as pavement sections are repaired.
  • Parking is restricted within construction areas but otherwise available to use. Please adhere to parking signage where posted.
  • Construction will continue at the College Avenue stations. Traffic is shifted around work zones and turn lane restrictions are in place.

Coming Soon:

  • One-block segments of College Avenue will be temporarily restricted adjacent to each station location for up to two hours each to allow the final layer of concrete to be poured on the station platforms. A tentative schedule for future weeks is below:
    • Kessler Ave station on June 25
    • 564th St station on June 26
    • 52nd St station on June 28
    • 46th St station on July 1
    • 42nd  St station on July 2

Continuing this Week:

  • Crews are modifying signals along Illinois St. No traffic restrictions are anticipated. Minor sidewalk and parking restrictions may be necessary.
  • Curb and sidewalk work will continue on 30th Street, requiring some lane restrictions.


Corridors Under Construction:

  • Meridian Street from 18th St. to 38th St.
  • Shelby St. from Hanna Ave. to Prospect St.
  • Capitol Ave. from 18th St. to Washington St.
  • Virginia Ave. from Shelby to Delaware St.
  • College Ave. from 38th St. to 66th St.
  • Illinois Street, Washington St to 18th St
  • 30th Street, Meridian St. to Illinois St.

* See Construction Forecast below for details.


Interactive Construction Map

Use this map by scrolling and clicking on the construction icons to understand what is happening in a particular place.



Click the buttons below to toggle which map items to display on the map.


Anticipated Construction Schedule

Draft schedule does not include utility relocations which may occur at any time throughout the construction process. Additional detailed schedules within each segment will be provided no less than three weeks in advance of construction activities.



Construction Forecast 

January 7

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Fri 1/11
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Fri 1/11
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Fri 12/21
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 2/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Mon 12/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Mon 1/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/7 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 14

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 1/30
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Sat 1/26
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Fri 1/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Tues 1/22
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Fri 12/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Mon 1/14
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/16
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/19
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Mon 1/14
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Sat 2/2
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/14
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Northbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia (Woodlawn): Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Station platform work @Northbound New Jersey: Wed 1/2 – Fri 3/1
Station platform work @Southbound New Jersey: Wed 1/2 – Fri 3/1
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1

January 21

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/6
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 2/15
Station foundation work @22nd Street Station: Mon 12/10 – Wed 2/4
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/8
Station foundation work @30th Street Station: Mon 11/26 – Wed 1/30
Erect station structure @30th Street Station: Wed 1/2 – Fri 2/1
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Mon 1/28
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Hannah Avenue Station: Mon 11/26 – Mon 1/14
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Wed 1/21
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Fri 3/1
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/1
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Fri 2/8
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 2/6 – Tues 3/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/5 – Fri 3/22
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Wed 2/6
Station platform work @Southbound New Jersey: Wed 1/2 – Tues 2/12
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1
College Ave. from 50th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1

January 28

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Tues 2/12
Erect station construction @18th Street Station: Tues 1/15 – Fri 2/22
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Tues 2/12
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Fri 2/8
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Mon 2/4
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station foundation work @38th Street Station: Mon 10/29 – Sat 2/9
Erect station structure @38th Street Station: Wed 1/16 – Thurs 2/28
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Thurs 1/31
Erect station structure @Hannah Avenue Station: Tues 1/15 – Fri 1/25
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Thurs 1/31
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Mon 2/4
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Sat 1/26
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 1/21 – Tues 2/12
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Thurs 1/24 – Fri 2/8
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Mon 3/11
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 3/1
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 2/4
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey: Wed 1/2 – Sat 2/9
Erect station structure @Northbound New Jersey: Mon 2/4 – Tues 2/19
Station platform work @Southbound New Jersey: Thurs 2/14 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @66th : Wed 2/6 – Thurs 2/28

February 4

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 –
Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 –
Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 –
Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 –
Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 –
Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Sat 2/9
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 –
Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 –
Sat 3/9
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 –
Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 –
Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 –
Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 –
Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Mon 3/11
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 1/14
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 –
Mon 2/11
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive):
Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Mon 1/28 – Tues 2/12
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station:
Thurs 2/7 – Sun 2/24
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 –
Sun 3/17
Station platform work @Northbound Virginia Ave. Station (Woodlawn):
Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Sat 4/20
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 –
Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Fri 2/1 – Mon 3/18
Station platform work @Northbound New Jersey:
Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey:
Mon 2/4 – Mon 2/18
Station platform work @Southbound New Jersey: Thurs 2/14 –
Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 11

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station foundation work @18th Street Station: Wed 12/17 – Wed 2/20
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/1
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Wed 2/20
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Mon 2/25
Station foundation work @22nd Street Station: Mon 12/10 – Tues 2/19
Erect station structure @22nd Street Station: Thurs 1/3 – Fri 2/15
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/14
Station foundation work @34th Street Station: Mon 11/5 – Fri 12/7
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Thu 3/14
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Thu 2/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 3/15
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21
Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/4 – Tues 2/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Mon 2/11 – Fri 3/22
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Wed 3/20
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Fri 3/1
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 3/29
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Sat 2/16
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Wed 2/6 – Fri 3/22
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/6 – Thurs 2/28
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 18

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Sun 3/10
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Mon 2/25
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Sat 3/2
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Sat 2/23
Erect station structure @344th Street Station: Wed 2/13 – Thurs 3/21
Station foundation work @38th Street Station: Mon 10/29 – Wed 2/20
Erect station structure @38th Street Station: Wed 1/16 – Sun 3/31
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Thurs 3/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/10
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/18 – Fri 4/19
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/27

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Northbound Virginia Ave. Station (Merrill): Fri 3/8 – Sun 4/7
Erect station structure @Southbound Virginia Ave. Station (Merrill): Wed 3/6 – Sun 3/31
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Tues 4/16
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Thurs 3/7
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 2/22
Roadway & Sidewalk improvements: Mon/11/26 – Fri 3/1 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Roadway & Sidewalk improvements: Mon, 12/3 – Fri 3/1 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Mon 3/11 – Sat 4/27

February 25

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Sun 3/10
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Thurs 2/28
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Sat 3/2
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Thurs 2/28
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Sun 3/31
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Fri 3/8
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Thurs 3/14
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 3/15
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Mon 2/18 – Wed 3/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Station platform work @Vermont Street Station: Wed 2/20 – Wed 3/20
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Mon 3/11 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Sun 3/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/25 – Wed 3/6

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 4/1
Erect station structure @Northbound Virginia Ave. Station (Merrill): Fri 3/8 – Sun 4/7
Erect station structure @Southbound Virginia Ave. Station (Merrill): Wed 3/6 – Sun 3/31
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 1/30 – Tues 4/16
Station platform work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Thurs 3/7
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Fri 2/22
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Tues 3/5 – Mon 3/11
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Thurs 2/14 – Fri 4/5
Station platform work @Southbound New Jersey: Mon 2/4 – Sat 3/2
Station platform work @Northbound New Jersey: Mon 2/18 – Sat 3/9
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Thurs 3/7 – Wed 3/13
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Wed 2/27 – Wed 3/6
Station platform work @Broad Ripple Ave. Station: Thurs 3/7 – Thurs 3/21
Station platform work @Kessler Ave. Station: Thurs 3/14 – Fri 4/5

 

 

 

March 4

Meridian Street from 18th St. to 38th St.
Traffic signal work: Mon 12/3 – Fri 12/21
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Station foundation work @18th Street Station: Wed 12/17 – Mon 2/25
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station construction @18th Street Station: Tues 1/15 – Wed 3/13
Station foundation work @Fall Creek Parkway Station: Mon 12/3 – Thurs 2/28
Erect station structure @Fall Creek Parkway Station: Wed 1/2 – Fri 3/8
Station foundation work @22nd Street Station: Mon 12/10 – Sat 2/23
Erect station structure @22nd Street Station: Thurs 1/3 – Sun 2/24
Station foundation work @30th Street Station: Mon 11/26 – Sat 2/23
Erect station structure @30th Street Station: Wed 1/2 – Thu 2/21
Station ramp work @34th Street Station: Mon 2/11 – Sat 3/9
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements: Mon 8/6 – December (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station foundation work @Hannah Avenue Station: Mon 11/26 – Mon 2/11
Erect station structure @Hannah Avenue Station: Tues 1/15 – Wed 2/6
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Station platform work @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/7 – Sun 2/17
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Thurs 3/21
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Mon 3/11
Station foundation work @Southbound Shelby Street Station (Garfield Park): Mon 11/19 – Fri 12/14
Station platform work @Southbound Shelby Street Station: Mon 10/29 – Fri 2/15
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Wed 3/27
Station foundation work @Northbound Shelby Street Station: Mon 10/29 – Sat 1/26
Erect station structure @Northbound Shelby Street Station: Wed 12/5 – Mon 12/17
Roadway & Sidewalk improvements: Mon 10/22 – Fri 12/28

Shelby St. from Raymond St. to Prospect St.
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/24
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Station platform work @Northbound Shelby Street Station (Pleasant Run Drive): Mon 11/5 – Mon 1/21
Erect station structure @Northbound Shelby Street Station (Pleasant Run Drive): Wed 12/12 – Fri 12/21

Capitol Ave. from 18th St. to Washington St.
Station platform work @9th Street Station: Thurs 2/28 – Wed 3/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 2/12 – Fri 3/15
Station platform work @18th Street Station: Tues 2/12 – Sat 3/9
Erect station structure @18th Street Station: Fri 3/15 – Mon 4/15
Station platform work @Vermont Street Station: Mon 3/11 – Tues 3/26
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Mon 4/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 2/25 – Mon 3/11

Virginia Ave. from Shelby to East St.
Station platform work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 – Tues 4/23
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Fri 3/15
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Mon 3/4 – Fri 4/19
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 3/18
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Mon 3/18 – Tues 3/26
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Sat 3/16
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Sat 3/16
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Fri 3/15 – Sat 3/23
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Signal work: Mon 2/4 – Wed 5/1
Station platform & ramp work @52nd Street Station: Wed 3/13 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 – Sun 3/10
Erect station structure @66th Street Station: Wed 3/6 – Mon 4/1
Station platform work @Broad Ripple Ave. Station: Fri 3/8 – Mon 3/25
Station platform work @Kessler Ave. Station: Fri 4/5 – Tues 4/30

March 11

Meridian Street from 18th St. to 38th St.
Station platform & ramp work @14th Street Station: Tues 2/19 –
Fri 4/5
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Wed 3/13
Station ramp work @34th Street Station: Mon 2/11 –
Fri 3/22
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 3/8
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 4/5
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 –
Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Wed 3/27

Shelby St. from Raymond St. to Prospect St.
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sun 3/24
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 –
Fri 3/22

Capitol Ave. from 18th St. to Washington St.
Station platform & ramp work @9th Street Station: Thurs 2/28 –
Sat 4/6
Erect station structure @9th Street Station: Thurs 3/21 – Mon 5/20
Station platform work @14th Street Station: Tues 2/19 – Thurs 3/14
Erect station structure @14th Street Station: Tues 3/19 –
Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station structure @18th Street Station: Fri 3/15 – Wed 4/24
Station platform work @Vermont Street Station: Mon 3/11 – Sat 3/30
Erect station structure @Vermont Street Station: Thurs 2/28 – Wed 3/20
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/1
Erect station structure @ Washington Street Station: Mon 3/4 – Mon 4/1
Signal work: Fri 1/4 – Mon 4/1
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements:
Mon 3/11 – Wed 3/20

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Station platform work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Mon 3/18
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –
Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
Wed 3/27
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Tues 3/19
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Thurs 3/21 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Mon 4/1
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 –
Fri 3/22
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Fri 3/22
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey:
Thurs 3/21 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @Park Station: Mon 3/25 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/18 – Sat 3/23
Temporary road closure Bungalow Street east of College Ave: Mon 3/18 – Sat 3/23
Lane restriction from 38th Street to Ruckle Street: Mon 3/18 – Tues 4/30
Station platform & ramp work @52nd Street Station: Wed 3/20 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 –
Wed 3/13
Erect station structure @66th Street Station: Wed 3/20 – Fri 4/26
Station platform work @Broad Ripple Ave. Station: Tues 3/12 – Sat 3/30
Station platform work @Kessler Ave. Station: Fri 4/5 – Tues 4/30
Signal work: Mon 2/4 – Wed 5/1

March 18

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Station ramp work @34th Street Station: Mon 2/11 – Tues 3/19
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Thurs 3/28
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Fri 4/5
Bus pad work @Troy Avenue: Sat 3/17 – Tues 4/9
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 1/28 – Fri 4/5
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Fri 3/29 – Mon 4/15
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Thurs 3/28 – Fri 5/10

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Station platform & ramp work @9th Street Station: Thurs 2/28 – Sat 4/6
Erect station structure @9th Street Station: Thurs 3/21 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 3/29
Erect station structure @14th Street Station: Tues 3/19 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station structure @18th Street Station: Fri 3/15 – Wed 4/24
Station platform work @Vermont Street Station: Mon 3/11 – Mon 4/8
Erect station structure @Vermont Street Station: Wed 4/3 – Fri 5/10
Station platform work @Washington Street Station: Wed 3/6 – Mon 4/8
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 3/20

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Wed 3/20
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Wed 3/20
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 3/27
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Tues 3/19
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Wed 3/20 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/30 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Fri 3/22
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Fri 3/22
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/20 – Wed 3/27
Roadway improvements: Mon 3/4 – Sat 3/16 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform work @Park Station: Mon 3/25 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 3/20 – Mon 4/1
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Fri 4/26
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 4/5
Station platform work @Broad Ripple Ave. Station: Mon 3/25 – Mon 4/8
Station platform work @Kessler Ave. Station: Wed 4/10 – Tues 4/30
Signal work: Mon 2/4 – Wed 5/1

March 25

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Tues 4/9 – Wed 4/17
Bus pad work @22nd Street Station: Mon 4/8 – Tues 4/16
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Sat 4/6 – Sun 4/14
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Wed 4/10 – Thurs 4/18
Bus pad work @34th Street Station: Thurs 4/11 – Fri 4/19
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Tues 4/9
Bus pad work @Troy Avenue: Fri 3/29 – Thurs 4/11
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Tues 4/9
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/15
Bus pad work @Shelby Street Station (Pleasant Run Drive): Wed 4/10 – Wed 4/17
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Fri 4/5
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Sat 4/6
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Sat 4/6
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 4/5
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Thurs 4/18
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 – Mon 4/8
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Mon 3/25

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Mon 3/25
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Mon 3/25
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Mon 3/25
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Mon 3/25
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform work @Park Station: Thurs 3/21 – Tues 4/12
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Tues 4/16 – Tues 5/7
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: Mon 3/25 – Thurs 4/18
Station platform work @Kessler Ave. Station: Wed 5/1 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 1

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station:
Wed 4/10 – Thurs 4/11
Bus pad work @22nd Street Station:
Tues 4/9 – Wed 4/10
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station:
Mon 4/8 – Tues 4/9
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station:
Thurs 4/11 – Fri 4/12
Bus pad work @34th Street Station:
Fri 4/12 – Sat 4/13
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 3/25 – Tues 4/9
Bus pad work @Troy Avenue: Fri 3/29 – Thurs 4/11
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 –
Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/15
Bus pad work @Shelby Street Station (Pleasant Run Drive):
Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 –
Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – 
Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 –
Mon 4/8
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 4/5
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – 
Mon 4/22
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 –
Wed 4/10
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Mon 3/25

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
 Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – 
Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – 
Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – 
Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform work @Park Station: Thurs 3/21 –
Mon 4/15
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Tues 4/16 – Tues 5/7
Station platform work @66th Street Station: Wed 2/13 – Wed 3/13
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: Mon 3/25 – Thurs 4/18
Station platform work @Kessler Ave. Station: Wed 5/1 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 8

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: 
Tues 4/16 – Fri 4/19
Bus pad work @22nd Street Station: 
Mon 4/15 – Thurs 4/18
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: 
Mon 4/15 – Wed 4/17
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: 
Wed 4/17 – Sat 4/20
Bus pad work @34th Street Station: 
Thurs 4/18 – Tues 4/23
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Fri 4/5
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue:
Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – 
Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Wed 4/24
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Sat 4/20
Bus pad work @Raymond Street:
Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): 
Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Fri 4/12
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – 
Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – 
Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – 
Fri 4/26
Erect station structure @Vermont Street Station: Tues 4/9 – Fri 5/31
Station platform & ramp work @Washington Street Station: Wed 3/6 – 
Wed 4/10
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 –
Sat 4/13

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 4/16
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 –
 Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Thurs 4/18
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – 
Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 4/19 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station platform @Park Station: Fri 4/19 – Tues 6/4
Station platform and ramp work @Park Station: Thurs 3/21 – 
Mon 4/15
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 5/1 – Tues 5/21
Station platform & ramp work @54th Street Station: Mon 4/22 – Wed 5/15

Station platform & ramp work @66th Street Station: Wed 2/13 – 
Mon 4/15
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 3/25 – Fri 6/14
Station platform& ramp work @Broad Ripple Ave. Station: 
Thurs 4/4 – Fri 5/10
Station platform work @Kessler Ave. Station:
Wed 4/17 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

April 15

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Tues 4/23 – Tues 4/30
Bus pad work @22nd Street Station:  Mon 4/22 – Mon 4/29
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 4/22 – Mon 4/29
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Tues 4/2 – Wed 5/1
Bus pad work @34th Street Station: Thurs 4/25 – Thurs 5/2
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Fri 4/19
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Mon 4/15
Station platform & ramp work @Northbound Shelby Street Station (Southern Ave. Station): Mon 11/19 – Wed 3/27
Erect station structure @Southbound Shelby Street Station: Mon 2/18 – Fri 3/29

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Fri 4/5 – Mon 5/20

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Wed 5/1
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Erect station structure @14th Street Station: Thurs 3/21 – Fri 5/10
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 5/3
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Fri 4/26
Erect station structure @Vermont Street Station: Mon 4/22 – Mon 5/13
Station platform & ramp work @Washington Street Station: Wed 3/6 – Tues 4/16
Erect station structure @ Washington Street Station: Thurs 4/4 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 4/1 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sat 4/13

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Mon 4/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 4/19 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform and ramp work @42nd Street Station: Wed 4/24 – Wed 5/1
Erect station platform @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @52nd Street Station: Mon 4/29 – Tues 5/21
Station platform & ramp work @54th Street Station: Mon 4/22 – Wed 5/15
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Mon 3/18 – Thurs 6/13
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/19
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Wed 5/1
Station platform work @Kessler Ave. Station: Tues 4/16 – Tues 5/21
Signal work: Mon 2/4 – Wed 5/1

Washington, Delaware and Maryland Streets
Resurfacing work @Washington St.: Thurs 4/18 – Mon 5/6
Resurfacing work @Maryland St.: Thurs 4/18 – Mon 5/6
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

April 22

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Wed 5/15– Thurs 5/16
Bus pad work @22nd Street Station:  Tues 5/14 – Wed 5/15
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/13 – Tues 5/14
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Thurs 5/16 – Fri 5/17
Bus pad work @34th Street Station: Fri 5/17 – Fri 5/18
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 4/22 – Tues 4/23
Erect station structure @9th Street Station: Fri 3/29 – Mon 5/20
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street : Fri 4/26 – Sat 4/27
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street : Fri 4/26 – Sat 4/27
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway & Sidewalk improvements: Mon 11/26 – Mon 5/6 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sun 5/5

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Wed 5/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Wed 5/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Station platform and ramp work @42nd Street Station: Fri 5/3 – Wed 5/22
Erect station platform @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26  Tues 5/21
Station platform & ramp work @52nd Street Station: Mon 4/29 – Tues 5/21
Station platform & ramp work @54th Street Station: Wed 4/24 – Fri 5/17
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 4/25
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Fri 4/26
Station platform work @Kessler Ave. Station: Tues 4/16 – Fri 5/10
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

April 30

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: 
Thurs 5/23 – Fri 5/24
Bus pad work @22nd Street Station: 
Wed 5/22 – Thurs 5/23
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: 
Tues 5/21 – Wed 5/22
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: 
Fri 5/24 – Sat 5/25
Bus pad work @34th Street Station: 
Sat 5/25 – Sun 5/26
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street:
Mon 4/29 – Tues 4/30
Erect station structure @9th Street Station:
Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street :
Wed 5/1 – Thurs 5/2
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street :
Wed 5/1 – Thurs 5/2
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 –
Sun 5/15(Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 –
Sat 5/11

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Wed 5/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 –
Sat 5/18 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station structure @Kessler Station: Fri 5/3 – Tues 5/28
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/1
Erect station structure @52 nd Street Station: Wed 5/15 – Sat 6/15

Station platform and ramp work @42nd Street Station:
Thurs 5/9 – Tues 6/4
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 
Thurs 5/16
Station platform & ramp work @52nd Street Station: 
Wed 5/1 – Sat 5/25
Station platform & ramp work @54th Street Station:
Fri 5/10 – Sun 6/9
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 –
Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Fri 4/26
Station platform work @Kessler Ave. Station: Tues 4/16 – Fri 5/10
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

May 6

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Wed 5/29 – Thurs 5/30
Bus pad work @22nd Street Station:  Tues 5/28 – Wed 5/29
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/27 – Tues 5/28
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Mon 5/20 – Fri 5/31
Bus pad work @34th Street Station: Fri 5/31 – Sat 6/1
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – May (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/6 – Tues 5/7
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street: Mon 5/6 – Tues 5/7
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street: Wed 5/8 – Thurs 5/9
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Sun 5/15(Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sun 5/19

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Sun 5/19 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Sat 5/18 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station structure @Kessler Station: Fri 5/3 – Tues 5/28
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/1
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/15
Station platform and ramp work @42nd Street Station: Thurs 5/9 – Tues 6/4
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 – Mon 5/27
Station platform & ramp work @52nd Street Station: Wed 5/1 – Sat 5/25
Erect station structure @54th Street Station: Fri 5/10 – Sun 6/9
Station platform & ramp work @54th Street Station: Wed 4/24 – Wed 5/22
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Sun 5/5
Station platform work @Kessler Ave. Station: Tues 4/16 – Fri 5/24
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Tues 5/14 – Tues 5/14
Pavement work @Maryland St.: Mon 5/13 – Mon 5/13
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

May 13

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station:  Tues 5/21 – Wed 5/22
Bus pad work @22nd Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station:  Tues 5/21 – Wed 5/22
Bus pad work @34th Street Station:  Wed 5/22 – Thurs 5/23
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – June (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 3/18 – Sun 4/14

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Sun 4/14

Capitol Ave. from 18th St. to Washington St.
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Sat 5/25
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/13 – Wed 5/15
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street:  Mon 5/13 – Wed 5/15
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street: Tues 5/14 – Thurs 5/16
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Sat 5/18
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Sun 6/2(Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Sun 5/19

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Mon 4/29
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –Fri 5/3
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Sat 4/20
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Wed 4/10
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Fri 5/24 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Fri 4/19
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Fri 4/5
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Fri 5/24 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Thurs 6/1
Erect station structure @Kessler Station: Fri 5/3 – Tues 5/28
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/8
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/15
Erect station structure @42nd Street Station: Sat 5/11 – Mon 6/10
Station platform and ramp work @42nd Street Station: Thurs 5/9 – Tues 6/4
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 – Mon 5/27
Station platform & ramp work @52nd Street Station: Wed 5/1 – Thurs 5/30
Erect station structure @54th Street Station: Fri 5/10 – Sun 6/9
Station platform & ramp work @54th Street Station: Wed 4/24 – Wed 5/22
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Thurs 5/16
Station platform work @Kessler Ave. Station: Tues 4/16 – Thurs 5/16
Signal work: Mon 2/4 – Mon 5/20

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Tues 5/14 – Tues 5/14
Pavement work @Maryland St.: Mon 5/13 – Mon 5/13
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

30th Street from Meridian Street to Illinois Street

Roadway improvements: Mon 5/20 – Mon 5/27

May 20

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Wed 5/22 – Thurs 5/23
Bus pad work @22nd Street Station: Tues 5/21 – Wed 5/22
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Thurs 5/23 – Fri 5/24
Bus pad work @34th Street Station: Fri 5/24 – Sat 5/25
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – June (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 2/18 – Thurs 5/16

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Fri 5/17

Capitol Ave. from 18th St. to Washington St.
Closure @ Walnut Street: Tues 5/21 – Fri 5/24
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Fri 5/24
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/13 – Wed 5/15
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street:  Mon 5/13 – Wed 5/15
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street: Tues 5/14 – Thurs 5/16
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Wed 5/29
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Wed 6/19 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 6/5

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Thurs 5/23
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 – Thurs 5/23
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Tues 5/21
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Tues 5/21
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Wed 6/12 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Wed 5/29
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Wed 5/29
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Wed 6/12 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Tues 6/25
Bus pad work @42nd Street Station: Tues 5/28 – Tues 5/28
Bus pad work @46th Street Station: Wed 5/29 – Wed 5/29
Bus pad work @52nd Street Station: Thurs 5/30 – Thurs 5/30
Bus pad work @54th Street Station: Fri 5/31 – Fri 5/31
Bus pad work @Kessler Ave. Station: Sat 6/1 – Sat 6/1
Bus pad work @Broad Ripple Ave. Station: Mon 6/3 – Mon 6/3
Erect station structure @Kessler Station: Wed 5/15 – Thurs 6/20
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/8
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/22
Erect station structure @42nd Street Station: Sat 5/11 – Sat 6/15
Station platform and ramp work @42nd Street Station: Wed 5/1 – Thurs 5/24
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 – Fri 5/24
Station platform & ramp work @52nd Street Station: Wed 5/1 – Sat 5/25
Erect station structure @54th Street Station: Fri 5/10 – Tues 6/11
Station platform & ramp work @54th Street Station: Wed 4/24 – Fri 5/17
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sun 5/21
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Thurs 5/16
Station platform work @Kessler Ave. Station: Tues 4/16 – Thurs 5/16
Signal work: Mon 2/4 – Sat 6/25

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Mon 5/20 – Thurs 5/23
Pavement work @Maryland St.: Wed 5/22 – Sat 6/1
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

30th Street from Meridian Street to Illinois Street

Roadway improvements: Mon 5/20 – Mon 5/27

May 27

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: 
Fri 5/24 – Fri 5/24
Bus pad work @22nd Street Station: 
Thurs 5/23 – Thurs 5/23
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: 
Tues 5/28 – Tues 5/28
Bus pad work @34th Street Station:
Sat 5/29 – Sat 5/29
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – June (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 2/18 – Thurs 5/16

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Fri 5/17

Capitol Ave. from 18th St. to Washington St.
Closure @ Walnut Street:
Wed 5/29 – Sat 6/1
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Fri 5/24
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/13 – Wed 5/15
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street:  Mon 5/13 – Wed 5/15
Erect station structure @14th Street Station: Thurs 3/21 – Fri 4/19
Bus pad work @18th Street: Tues 5/14 – Thurs 5/16
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Fri 4/22
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Wed 5/29
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Wed 6/19 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 6/5

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 –
Sat 6/1
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 –
Sat 6/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 –
Fri 5/31
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 –
Fri 5/31
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 –
Sat 6/15 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 –
Mon 6/3
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 –
Mon 6/3
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – 
Sat 6/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Tues 6/25
Bus pad work @42nd Street Station:
Mon 6/3 – Mon 6/3
Bus pad work @46th Street Station:
Tues 6/4 – Tues 6/4
Bus pad work @52nd Street Station:
Wed 6/5 – Wed 6/5
Bus pad work @54th Street Station: Thurs 6/6 – Thurs 6/6
Bus pad work @Kessler Ave. Station:
Mon 6/10 – Mon 6/10
Bus pad work @Broad Ripple Ave. Station:
Tues 6/11 – Tues 6/11
Erect station structure @Kessler Station: Wed 5/15 – Thurs 6/20
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/8
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/22
Erect station structure @42nd Street Station: Sat 5/11 – Sat 6/15
Station platform and ramp work @42nd Street Station: Wed 5/1 –
Fri 5/31
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 –
Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 5/1 –
Fri 5/31
Erect station structure @54th Street Station: Fri 5/10 – Tues 6/11
Station platform & ramp work @54th Street Station: Wed 4/24 – Fri 5/17
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 –
Sat 6/1
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Thurs 5/16
Station platform work @Kessler Ave. Station: Tues 4/16 – Thurs 5/16
Signal work: Mon 2/4 – Sat 6/25

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Tues 5/28 – Fri 5/31
Pavement work @Maryland St.:
walnut
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 4/29 – Mon 4/29
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

30th Street from Meridian Street to Illinois Street
Roadway improvements: Mon 5/20 – Mon 5/27

 

June 3

Meridian Street from 18th St. to 38th St.
Station ramp work @Meridian Street: Sun 3/10 – Fri 4/19
Bus pad work @Fall Creek Avenue Station: Fri 5/24 – Fri 5/24
Bus pad work @22nd Street Station: Thurs 5/23 – Thurs 5/23
Station platform & ramp work @14th Street Station: Tues 2/19 – Fri 4/5
Bus pad work @18th Street Station: Mon 5/20 – Tues 5/21
Station platform & ramp work @18th Street Station: Tues 2/12 – Fri 3/29
Erect station construction @18th Street Station: Tues 1/15 – Fri 3/15
Bus pad work @30th Street Station: Fri 5/31 – Fri 5/31
Bus pad work @34th Street Station: Sun 6/2 – Sun 6/2
Station ramp work @34th Street Station: Mon 2/11 – Sun 3/24
Erect station structure @34th Street Station: Wed 2/13 – Thurs 3/21
Station foundation and ramp work @38th Street Station: Mon 10/29 – Sat 4/13
Erect station structure @38th Street Station: Wed 1/16 – Mon 3/25
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – June (Additional Detail Above)

Shelby St. from Hanna Ave. to Troy Ave.
Bus pad work @Hannah Avenue: Mon 4/8 – Mon 4/15
Bus pad work @Troy Avenue: Mon 4/8 – Mon 4/15
Station platform work @Southbound Troy Avenue Station: Mon 10/22 – Wed 1/21
Erect station structure @Southbound Troy Avenue Station: Sat 12/1 – Thurs 1/17
Station foundation work @Northbound Troy Avenue Station: Mon 11/5 – Mon 2/11
Erect station structure @Northbound Troy Avenue Station: Tues 12/18 – Mon 1/21

Shelby St. from Troy Ave. to Raymond St. (Nelson Ave. to Southern Ave.)
Temporary road closure: Shelby Street (Southern Ave.): Wed 4/3 – Wed 4/10
Bus pad work @Shelby Street Station (Southern Ave. Station): Wed 4/3 – Wed 4/10
Erect station structure @Northbound Shelby Street Station (Southern Ave. Station): Tues 3/19 – Sun 4/14
Erect station structure @Southbound Shelby Street Station (Southern Ave. Station): Mon 2/18 – Thurs 5/16

Shelby St. from Raymond St. to Prospect St.
Temporary road closure: Shelby Street (Pleasant Run Dr.): Sat 4/13 – Mon 4/22
Bus pad work @Raymond Street: Mon 4/1 – Mon 4/8
Bus pad work @Shelby Street Station (Pleasant Run Drive): Sat 4/13 – Sat 4/20
Station platform & ramp work @Southbound Shelby Street Station (Pleasant Run Drive): Mon 2/11 – Sat 4/20
Erect station structure @Southbound Shelby Street Station (Pleasant Run Drive): Wed 4/3 – Fri 5/17

Capitol Ave. from 18th St. to Washington St.
Closure @ Walnut Street: Wed 5/29 – Sat 6/1
Signal work @Illinois Street: Wed 3/27 – Wed 5/1
Signal work 18th Street to Washington Street: Fri 1/4 – Mon 5/20
Erect station structure @Washington Street Station: Mon 4/8 – Fri 5/24
Station platform & ramp work @9th Street Station: Thurs 2/28 – Wed 4/10
Bus pad work @9th Street: Mon 5/13 – Wed 5/15
Erect station structure @9th Street Station: Mon 3/25 – Wed 5/1
Station platform & ramp work @14th Street Station: Tues 2/19 – Wed 4/10
Bus pad work @14th Street:  Mon 5/13 – Wed 5/15
Erect station structure @14th Street Station: Thurs 3/21 – Thurs 6/6
Bus pad work @18th Street: Tues 5/14 – Thurs 5/16
Station platform & ramp work @18th Street Station: Tues 2/12 – Wed 4/10
Erect station structure @18th Street Station: Wed 3/20 – Thurs 6/6
Bus pad work @Vermont Street: Wed 4/24 – Thurs 4/25
Station platform & ramp work @Vermont Street Station: Mon 3/11 – Sat 4/20
Erect station structure @Vermont Street Station: Mon 4/22 – Wed 5/29
Station platform & ramp work @Washington Street Station: Wed 3/6 – Sat 4/20
Erect station structure @ Washington Street Station: Mon 4/8 – Fri 5/10
Roadway, ADA ramp work & Sidewalk improvements: Mon 11/26 – Wed 6/19 (Additional Detail Above)

Virginia Ave. from East St. to Virginia Ave.
Roadway improvements: Mon 2/18 – Wed 2/17

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Mon 6/10

Virginia Ave. from Shelby to East St.
Station platform & ramp work @Southbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Station platform & ramp work @Northbound Virginia Ave. Station (Merrill): Tues 2/12 – Sat 3/23
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Sat 6/1
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 – Sat 6/1
Erect station structure @Southbound Virginia Ave. Station (Woodlawn): Wed 2/27 – Fri 5/31
Station platform & ramp work @Northbound Virginia Ave. Station (Woodlawn): Thurs 2/7 – Wed 4/3
Erect station structure @Northbound Virginia Ave. Station (Woodlawn): Tues 3/12 – Fri 5/31
Station platform & ramp work @Southbound Virginia Ave. Station (Woodlawn): Wed 1/2 – Wed 4/3
Bus pad work (temporary road closure) @Virginia Ave. & Woodlawn Ave.: Sat 3/23 – Sun 3/31
Roadway improvements: Mon 3/4 – Sat 6/19 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Signal work from Shelby to Delaware: Thurs 1/24 – Sat 3/16
Erect station structure @Southbound New Jersey: Mon 3/18 – Mon 6/3
Station platform & ramp work @Southbound New Jersey: Mon 2/4 – Wed 4/3
Station platform & ramp work @Northbound New Jersey: Mon 2/18 – Wed 4/3
Erect station structure @Northbound New Jersey: Thurs 3/7 – Mon 6/3
Bus pad work (temporary road closure) @Virginia Ave. & New Jersey: Wed 3/27 – Wed 4/3
Roadway improvements: Mon 3/4 – Sat 6/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Tues 6/25
Bus pad work @42nd Street Station: Mon 6/3 – Mon 6/3
Bus pad work @46th Street Station: Tues 6/4 – Tues 6/4
Bus pad work @52nd Street Station: Wed 6/5 – Wed 6/5
Bus pad work @54th Street Station: Thurs 6/6 – Thurs 6/6
Bus pad work @Kessler Ave. Station: Mon 6/10 – Mon 6/10
Bus pad work @Broad Ripple Ave. Station: Tues 6/11 – Tues 6/11
Erect station structure @Kessler Station: Wed 5/15 – Thurs 6/20
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/8
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/22
Erect station structure @42nd Street Station: Sat 5/11 – Sat 6/15
Station platform and ramp work @42nd Street Station: Wed 5/1 – Fri 5/31
Erect station structure @Park Station: Wed 4/10 – Wed 5/15
Station platform and ramp work @Park Station: Thurs 3/21 – Sun 4/21
Temporary road closure 54th Street west of College Ave to alley: Mon 3/25 – Sat 3/31
Temporary road closure Bungalow Street east of College Ave: Mon 4/1 – Sat 4/7
Lane restriction from 38th Street to Ruckle Street: Sat 3/16 – Fri 5/31
Station platform & ramp work @46th Street Station: Fri 4/26 – Fri 5/31
Station platform & ramp work @52nd Street Station: Wed 5/1 – Fri 5/31
Erect station structure @54th Street Station: Fri 5/10 – Tues 6/11
Station platform & ramp work @54th Street Station: Wed 4/24 – Fri 5/17
Station platform & ramp work @66th Street Station: Wed 2/13 – Mon 4/15
Erect station structure @66th Street Station: Wed 4/3 – Thurs 5/2
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sat 6/1
Station platform& ramp work @Broad Ripple Ave. Station: Thurs 4/4 – Thurs 5/16
Station platform work @Kessler Ave. Station: Tues 4/16 – Thurs 5/16
Signal work: Mon 2/4 – Sat 6/25

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Tues 5/28 – Sun 6/2
Pavement work @Walnut St: Mon 6/10 – Sun 6/16
Resurfacing work @Washington St.: Tues 4/30 – Tues 4/30
Resurfacing work @Maryland St.: Mon 6/17 – Sun 6/23
Resurfacing work @Delaware St.: Thurs 4/18 – Mon 5/6

30th Street from Meridian Street to Illinois Street
Roadway improvements: Mon 5/20 – Mon 5/27

June 10

Meridian Street from 18th St. to 38th St.
Bus pad work @34th Street Station: Sun 6/2 – Sun 6/2
Roadway & Sidewalk improvements from 18th to 30th Street: Mon 8/13 – July (Additional Detail Above)

Capitol Ave. from 18th St. to Washington St.
Closure @ Walnut Street: Wed 5/29 – Sat 6/1
Erect station structure @14th Street Station: Thurs 3/21 – Thurs 6/6
Erect station structure @18th Street Station: Wed 3/20 – Thurs 6/6
Roadway work: Mon 11/26 – Fri 7/5 (Additional Detail Above)

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 6/19

Virginia Ave. from Shelby to East St.
Erect station structure @Northbound Virginia Ave. Station (Merrill): Tues 3/26 – Sat 6/1
Erect station structure @Southbound Virginia Ave. Station (Merrill): Tues 3/26 – Sat 6/1
Roadway improvements: Mon 3/4 – Sat 6/19 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Erect station structure @Northbound New Jersey: Thurs 3/7 – Mon 6/3
Roadway improvements: Mon 3/4 – Sat 6/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Wed 7/31
Bus pad work @42nd Street Station: Wed 6/5 – Wed 6/5
Bus pad work @46th Street Station: Fri 6/7 – Fri 6/7
Bus pad work @52nd Street Station: Mon 6/10 – Mon 6/10
Bus pad work @54th Street Station: Thurs 6/6 – Thurs 6/6
Bus pad work @Kessler Ave. Station: Tues 6/11 – Tues 6/11
Bus pad work @Broad Ripple Ave. Station: Wed 6/12 – Wed 6/12
Erect station structure @Kessler Station: Wed 5/15 – Thurs 6/20
Erect station structure @46th Street Station: Wed 5/8 – Sat 6/8
Erect station structure @52nd Street Station: Wed 5/15 – Sat 6/22
Erect station structure @42nd Street Station: Sat 5/11 – Sat 6/15
Erect station structure @54th Street Station: Fri 5/10 – Tues 6/11
Erect station structure @Broad Ripple Ave. Station: Mon 4/22 – Sat 6/1
Signal work: Mon 2/4 – Sat 6/25

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Fri 6/14 – Wed 6/19
Pavement work @Walnut St: Mon 6/10 – Sun 6/16
Resurfacing work @Maryland St.: Thurs 6/20 – Mon 6/24

30th Street from Meridian Street to Illinois Street
Signal work @Illinois Street: Wed 3/27 – Sun 6/23
Sideway, curb, and driveway work: Mon 6/3 – Mon 6/17

June 17

Meridian Street from 18th St. to 38th St.
Bus pad work @34th Street Station: Sun 6/2 – Sun 6/2
Roadway improvements from 18th to 30th Street: Mon 8/13 – July (Additional Detail Above)

Capitol Ave. from 18th St. to Washington St.
Erect station structure @14th Street Station: Thurs 3/21 – Thurs 6/6
Erect station structure @18th Street Station: Wed 3/20 – Thurs 6/6
Roadway work: Mon 11/26 – Fri 7/5 (Additional Detail Above)

Shelby St. from Hanna Ave. to Virginia Ave.
Roadway improvements: Mon 3/11 – Wed 6/26

Virginia Ave. from Shelby to East St.
Roadway improvements: Mon 3/4 – Wed 6/26 (Additional Detail Above)

Virginia Ave. from East St. to Delaware St.
Erect station structure @Northbound New Jersey: Thurs 3/7 – Mon 6/3
Roadway improvements: Mon 3/4 – Sat 6/15 (Additional Detail Above)

College Ave. from 38th St. to 66th St.
Roadway Improvements: Mon 2/4 – Wed 7/31
Bus pad work @46th Street Station: Fri 6/7 – Fri 6/7
Bus pad work @52nd Street Station: Mon 6/10 – Mon 6/10
Bus pad work @54th Street Station: Thurs 6/6 – Thurs 6/6
Bus pad work @Kessler Ave. Station: Tues 6/11 – Tues 6/11
Bus pad work @Broad Ripple Ave. Station: Wed 6/12 – Wed 6/12
Signal work: Mon 2/4 – Sat 6/25

Washington, Delaware and Maryland Streets
Pavement work @Washington St: Fri 6/21 – Wed 7/7
Closure @Walnut St: Mon 6/10 – Mon 6/24
Resurfacing work @Maryland St.: Thurs 6/27 – Tues 7/2

30th Street from Meridian Street to Illinois Street
Signal work @Illinois Street: Wed 3/27 – Sun 6/23
Sideway, curb, and driveway work: Mon 6/3 – Wed 6/26

 

 

 

Construction of the Red Line began in June 2018. You can view all published 2018 construction forecast here!

 

Interested in bid opportunities with IndyGo?